Artikel 12 Hoofdwegennet | Categorie | Totaal mutatie | 2013 | 2014 | 2015 | 2016 | 2017 | 2018 | 2019 | 2020 | 2021 | 2022 | 2023 | 2024 | 2025 | 2026 | 2027 | 2028 | Toelichting |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Ontwerpbegroting 2013 artikelonderdeel 12.01 Verkeersmgmt. |
|
| 22.072 | 18.733 | 20.539 | 20.412 | 19.700 | 19.700 | 19.701 | 19.700 | 19.701 | 19.701 | 19.701 | 22.290 | 22.290 | 22.290 | 22.290 | 22.290 | |
Mutaties voorjaarsnota 2013 |
|
| – 1.499 | – 313 | – 658 | – 531 | 180 | 180 | 181 | 180 | 227 | 227 | 227 | – 2.363 | – 2.363 | – 2.363 | – 2.363 | – 2.363 | |
Stand eerste suppletoire wet 2013 artikelonderdeel 12.01 Verkeersmgmt. |
|
| 20.573 | 18.420 | 19.881 | 19.881 | 19.880 | 19.880 | 19.882 | 19.880 | 19.928 | 19.928 | 19.928 | 19.927 | 19.927 | 19.927 | 19.927 | 19.927 | |
Indexering 2013 | Intens./extens. | 5.631 | 389 | 353 | 377 | 377 | 377 | 377 | 377 | 377 | 373 | 347 | 333 | 320 | 293 | 294 | 291 | 376 | 2 |
Overboeking binnen artikel 12 | neutraal | 1.664 | 832 | 416 | 416 | 3 | |||||||||||||
Mutaties Miljoenennota 2014 |
| 1.221 | 769 | 793 | 377 | 377 | 377 | 377 | 377 | 373 | 347 | 333 | 320 | 293 | 294 | 291 | 376 | ||
Stand ontwerpbegroting 2014 artikelonderdeel 12.01 Verkeersmgmt. |
|
| 21.794 | 19.189 | 20.674 | 20.258 | 20.257 | 20.257 | 20.259 | 20.257 | 20.301 | 20.275 | 20.261 | 20.247 | 20.220 | 20.221 | 20.218 | 20.303 | |
Ontwerpbegroting 2013 artikelonderdeel 12.02 Beheer, onderh & verv. |
|
| 413.384 | 494.537 | 350.416 | 361.701 | 475.925 | 472.235 | 468.503 | 471.333 | 438.022 | 523.691 | 523.692 | 522.636 | 522.638 | 522.636 | 522.636 | 534.812 | |
Mutaties voorjaarsnota 2013 |
| 140.491 | 136.224 | 218.946 | 109.831 | 31.085 | 16.861 | 29.516 | 26.579 | – 20.075 | – 105.846 | – 105.846 | – 99.752 | – 68.452 | – 68.452 | – 68.452 | – 76.290 | ||
Stand eerste suppletoire wet 2013 artikelonderdeel 12.02 Beheer, onderh & verv. |
|
| 553.875 | 630.761 | 569.362 | 471.532 | 507.010 | 489.096 | 498.019 | 497.912 | 417.947 | 417.845 | 417.846 | 422.884 | 454.186 | 454.184 | 454.184 | 458.522 | |
Indexering 2013 | Intens./extens. | 119.793 | 8.563 | 10.454 | 9.004 | 7.485 | 8.014 | 7.723 | 7.862 | 7.862 | 6.344 | 6.258 | 6.211 | 6.390 | 6.818 | 6.820 | 6.812 | 7.173 | 2 |
Overboeking binnen artikel 12 | neutraal | 2.796 | – 508 | 2.723 | 581 | 3 | |||||||||||||
Netwerkoverstijgende kosten | Intens./extens. | – 105.607 | – 9.482 | – 8.796 | – 7.345 | – 16.065 | – 14.415 | – 6.011 | – 8.701 | – 8.707 | – 8.763 | – 8.661 | – 8.661 | 4 | |||||
DBFM N33 Assen-Zuidbroek | Intens./extens. | – 44.224 | – 2.764 | – 2.764 | – 2.764 | – 2.764 | – 2.764 | – 2.764 | – 2.764 | – 2.764 | – 2.764 | – 2.764 | – 2.764 | – 2.764 | – 2.764 | – 2.764 | – 2.764 | – 2.764 | 18 |
DBFM A1/A6 SAA | Intens./extens. | – 78.400 | – 4.900 | – 4.900 | – 4.900 | – 4.900 | – 4.900 | – 4.900 | – 4.900 | – 4.900 | – 4.900 | – 4.900 | – 4.900 | – 4.900 | – 4.900 | – 4.900 | – 4.900 | – 4.900 | 20 |
Mutaties Miljoenennota 2014 |
|
| – 9.091 | – 6.006 | – 3.282 | – 15.663 | – 14.065 | – 5.952 | – 8.503 | – 8.509 | – 10.083 | – 10.067 | – 10.114 | – 1.274 | – 846 | – 844 | – 852 | – 491 | |
Stand ontwerpbegroting 2014 artikelonderdeel 12.02 Beheer, onderh & verv. |
|
| 544.784 | 624.755 | 566.080 | 455.869 | 492.945 | 483.144 | 489.516 | 489.403 | 407.864 | 407.778 | 407.732 | 421.610 | 453.340 | 453.340 | 453.332 | 458.031 | |
Ontwerpbegroting 2013 artikelonderdeel 12.03 Aanleg |
|
| 1.451.135 | 1.595.469 | 895.245 | 1.858.548 | 1.405.260 | 1.223.702 | 1.861.594 | 2.239.198 | 1.193.710 | 1.239.224 | 822.631 | 675.887 | 205.970 | 148.541 | 146.211 | 123.543 | |
Mutaties voorjaarsnota 2013 |
|
| – 223.503 | – 245.662 | – 268.520 | – 932.007 | – 175.732 | – 3.129 | – 61.106 | 239.152 | – 996 | 355.225 | 508.273 | 537.093 | 845.867 | 838.514 | 11.026 | – 39.823 | |
Stand eerste suppletoire wet 2013 artikelonderdeel 12.03 Aanleg |
|
| 1.227.632 | 1.349.807 | 626.725 | 926.541 | 1.229.528 | 1.220.573 | 1.800.488 | 2.478.350 | 1.192.714 | 1.594.449 | 1.330.904 | 1.212.980 | 1.051.837 | 987.055 | 157.237 | 83.720 | |
Desaldering | desaldering | 100 | 100 | 1 | |||||||||||||||
Indexering 2013 | Intens./extens. | 243.544 | 21.538 | 21.415 | 19.365 | 26.128 | 27.060 | 20.447 | 18.735 | 12.114 | 18.259 | 20.552 | 19.402 | 7.708 | 4.078 | 4.897 | 931 | 915 | 2 |
Overboeking binnen artikel 12 | neutraal | – 5.460 | – 824 | – 666 | – 3.389 | – 581 | 3 | ||||||||||||
Overboeking binnen Infrastructuurfonds | Intens./extens. | 4.252 | 5.356 | 2.280 | 1.135 | – 63.500 | 63.500 | – 4.519 | 5 | ||||||||||
Overboeking HXII – IF artikel 12 | Intens./extens. | – 12.757 | – 3.328 | – 32 | – 232 | – 3.301 | – 5.512 | – 32 | – 32 | – 32 | – 32 | – 32 | – 32 | – 32 | – 32 | – 32 | – 32 | – 32 | 6 |
DBFM N33 Assen-Zuidbroek | Intens./extens. | – 186.960 | – 69.201 | – 117.759 | 18 | ||||||||||||||
MJPO | Intens./extens. | – 168.004 | – 9.904 | – 19.772 | – 19.766 | – 19.763 | – 19.761 | – 19.755 | – 19.756 | – 19.755 | – 19.772 | 19 | |||||||
DBFM A1/A6 SAA | Intens./extens. | -802.027 | -11.208 | -50.947 | -175.259 | -441.204 | -123.409 | – 6.130 | – 6.130 | 6.130 | 6.130 | 20 | |||||||
Kasritme regiobijdrage | Desaldering | 0 | – 29.281 | 209.281 | – 80.000 | – 100.000 | 21 | ||||||||||||
Overboeking binnen artikel 12 | neutraal | 391 | – 12.882 | 41.055 | – 3.604 | – 3.604 | – 3.604 | – 3.604 | – 3.604 | – 3.604 | – 3.604 | – 2.948 | 0 | 0 | 0 | 0 | 0 | 391 | 22 |
A4 Delft Schiedam en A10 2e Coentunnel | Intens./extens. | – 91.000 | – 11.229 | 7.475 | – 24.969 | 7.631 | – 2.183 | – 2.283 | – 2.283 | – 2.183 | – 40.139 | – 2.283 | 461 | – 1.063 | – 1.063 | – 1.063 | – 1.063 | – 14.763 | 23 |
Leenconstructie wegen– reg/lok. | Intens./extens. | 0 | – 5.686 | – 173.268 | – 32.753 | 24.581 | 63.858 | 49.203 | 52.828 | 21.237 | 24 | ||||||||
Areaalgroei (artikel 18) | Intens./extens. | 797.534 | 58.245 | 58.245 | 58.245 | 58.245 | 58.245 | 31.770 | 442.770 | 31.770 | 25 | ||||||||
Meevallers A2/ZSM | Intens./extens. | – 69.300 | – 22.000 | – 15.000 | – 32.300 | 26 | |||||||||||||
Mutaties Miljoenennota 2014 |
|
| – 81.678 | – 148.460 | 7.328 | – 447.231 | – 251.148 | – 85.472 | 1.000 | – 183.007 | 49.834 | 84.479 | 122.171 | 94.300 | 94.301 | 37.053 | 418.332 | – 1.491 | |
Stand ontwerpbegroting 2014 artikelonderdeel 12.03 Aanleg |
|
| 1.145.954 | 1.201.347 | 634.053 | 479.310 | 978.380 | 1.135.101 | 1.801.488 | 2.295.343 | 1.242.548 | 1.678.928 | 1.453.075 | 1.307.279 | 1.146.138 | 1.024.108 | 575.569 | 82.229 | |
Ontwerpbegroting 2013 artikelonderdeel 12.04 GIV/PPS |
|
| 420.256 | 566.737 | 508.980 | 251.390 | 188.606 | 176.441 | 177.205 | 178.213 | 174.459 | 150.938 | 208.977 | 172.637 | 172.231 | 169.899 | 111.513 | 111.513 | |
Mutaties voorjaarsnota 2013 |
|
| – 82.652 | – 13.671 | – 27.382 | 149.400 | – 5.021 | 8.690 | 8.677 | 8.638 | 6.949 | 10.026 | – 37.474 | 60.919 | – 6.528 | – 6.528 | – 7.634 | – 22.025 | |
Stand eerste suppletoire wet 2013 artikelonderdeel 12.04 GIV/PPS |
|
| 337.604 | 553.066 | 481.598 | 400.790 | 183.585 | 185.131 | 185.882 | 186.851 | 181.408 | 160.964 | 171.503 | 233.556 | 165.703 | 163.371 | 103.879 | 89.488 | |
Indexering 2013 | Intens./extens. | 64.629 | 5.807 | 9.176 | 7.990 | 6.649 | 3.046 | 3.071 | 3.084 | 3.100 | 3.010 | 2.671 | 2.845 | 4.126 | 3.007 | 3.007 | 2.020 | 2.020 | 2 |
DBFM N33 Assen–Zuidbroek | Intens./extens. | 239.345 | 11.809 | 44.577 | 13.039 | 13.039 | 13.039 | 13.039 | 13.039 | 13.056 | 13.056 | 13.056 | 13.056 | 13.056 | 13.121 | 13.121 | 13.121 | 13.121 | 18 |
DBFM A1/A6 SAA | Intens./extens. | 859.264 | 3.321 | 10.101 | 10.101 | 10.101 | 255.360 | 51.747 | 51.747 | 51.747 | 51.747 | 51.747 | 51.934 | 51.934 | 51.934 | 51.934 | 51.934 | 51.875 | 20 |
Overboeking binnen artikel 12 | neutraal | 0 | 12.882 | – 41.055 | 3.604 | 3.604 | 3.604 | 3.604 | 3.604 | 3.604 | 3.604 | 2.948 | 22 | ||||||
A4 Delft Schiedam en A10 2e Coentunnel | Intens./extens. | 122.444 | 11.229 | 14.525 | 39.969 | 24.669 | 2.183 | 2.283 | 2.283 | 2.183 | 2.283 | 2.283 | – 461 | 1.063 | 1.063 | 1.063 | 1.063 | 14.763 | 23 |
Mutaties Miljoenennota 2014 |
|
| 45.048 | 37.324 | 74.703 | 58.062 | 277.232 | 73.744 | 73.757 | 73.690 | 73.700 | 72.705 | 67.374 | 70.179 | 69.125 | 69.125 | 68.138 | 81.779 | |
Stand ontwerpbegroting 2014 artikelonderdeel 12.04 GIV/PPS |
|
| 382.652 | 590.390 | 556.301 | 458.852 | 460.817 | 258.875 | 259.639 | 260.541 | 255.108 | 233.669 | 238.877 | 303.735 | 234.828 | 232.496 | 172.017 | 171.267 | |
Ontwerpbegroting 2013 artikelonderdeel 12.05 Verk.& Planuitw. voor tracebesl. | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties voorjaarsnota 2013 |
|
| 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
Stand eerste suppletoire wet 2013 artikelonderdeel 12.05 Verk.& Planuitw. voor tracebesl. |
|
| 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
Mutaties Miljoenennota 2014 |
|
| 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
Stand ontwerpbegroting 2014 artikelonderdeel 12.05 Verk.& Planuitw. voor tracebesl. |
|
| 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
|
| ||||||||||||||||||
Ontwerpbegroting 2013 artikelonderdeel 12.06 Netwerk HWN |
|
| 422.016 | 396.659 | 382.425 | 379.372 | 376.644 | 374.218 | 373.970 | 373.898 | 374.570 | 374.570 | 374.570 | 375.204 | 375.204 | 375.204 | 375.204 | 375.204 | |
Mutaties voorjaarsnota 2013 |
|
| 13.130 | 9.114 | 6.015 | 3.812 | 1.464 | 1.449 | 1.447 | 1.447 | 1.644 | 2.052 | 2.277 | 2.485 | 2.920 | 2.909 | 2.948 | 1.584 | |
Stand eerste suppletoire wet 2013 artikelonderdeel 12.06 Netwerk HWN |
|
| 435.146 | 405.773 | 388.440 | 383.184 | 378.108 | 375.667 | 375.417 | 375.345 | 376.214 | 376.622 | 376.847 | 377.689 | 378.124 | 378.113 | 378.152 | 376.788 | |
Indexering 2013 | Intens./extens. | 14.189 | 947 | 886 | 876 | 878 | 878 | 878 | 878 | 878 | 880 | 880 | 880 | 890 | 890 | 890 | 890 | 890 | 2 |
Overboeking binnen artikel 12 | neutraal | 1.000 | 500 | 250 | 250 | 3 | |||||||||||||
Loonbijstelling 2013 | Intens./extens. | 5.606 | 393 | 368 | 353 | 350 | 347 | 345 | 345 | 345 | 345 | 345 | 345 | 345 | 345 | 345 | 345 | 345 | 14 |
Overboeking HXII – IF artikel 12 | Intens./extens. | – 568 | – 142 | – 142 | – 142 | – 142 | 6 | ||||||||||||
Mutaties Miljoenennota 2014 |
|
| 1.698 | 1.362 | 1.337 | 1.086 | 1.225 | 1.223 | 1.223 | 1.223 | 1.225 | 1.225 | 1.225 | 1.235 | 1.235 | 1.235 | 1.235 | 1.235 | |
Stand ontwerpbegroting 2014 artikelonderdeel 12.06 Netwerk HWN |
|
| 436.844 | 407.135 | 389.777 | 384.270 | 379.333 | 376.890 | 376.640 | 376.568 | 377.439 | 377.847 | 378.072 | 378.924 | 379.359 | 379.348 | 379.387 | 378.023 | |
|
| ||||||||||||||||||
Ontwerpbegroting 2013 artikelonderdeel 12.07 Investeringsruimte |
|
| 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
Mutaties voorjaarsnota 2013 |
|
| 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 846.208 | 1.037.381 | |
Stand eerste suppletoire wet 2013 artikelonderdeel 12.07 Investeringsruimte |
|
| 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 846.208 | 1.037.381 | |
Indexering 2013 | Intens./extens. | – 454.973 | – 37.766 | – 42.732 | – 38.043 | – 41.956 | – 39.817 | – 32.936 | – 31.268 | – 24.883 | – 29.196 | – 31.260 | – 30.113 | – 19.885 | – 15.537 | – 16.360 | – 11.283 | – 11.938 | 2 |
Overboeking binnen Infrastructuurfonds | Intens./extens. | 4.519 | 4.519 | 5 | |||||||||||||||
MJPO | Intens./extens. | 168.004 | 9.904 | 19.772 | 19.766 | 19.763 | 19.761 | 19.755 | 19.756 | 19.755 | 19.772 | 19 | |||||||
Overboeking binnen artikel 12 | neutraal | – 391 | – 391 | 22 | |||||||||||||||
A4 Delft Schiedam en A10 2e Coentunnel | Intens./extens. | – 31.444 | – 22.000 | – 15.000 | – 32.300 | 37.856 | 23 | ||||||||||||
Areaalgroei (artikel 18) | Intens./extens. | – 411.000 | – 411.000 | 25 | |||||||||||||||
Meevallers A2/ZSM | Intens./extens. | 69.300 | 22.000 | 15.000 | 32.300 | 26 | |||||||||||||
Mutaties Miljoenennota 2014 |
|
| – 37.766 | – 42.732 | – 38.043 | – 41.956 | – 39.817 | – 32.936 | – 31.268 | – 14.979 | 28.432 | – 11.494 | – 10.350 | – 124 | 4.218 | 3.396 | – 398.009 | 7.443 | |
Stand ontwerpbegroting 2014 artikelonderdeel 12.07 Investeringsruimte |
|
| – 37.766 | – 42.732 | – 38.043 | – 41.956 | – 39.817 | – 32.936 | – 31.268 | – 14.979 | 28.432 | – 11.494 | – 10.350 | – 124 | 4.218 | 3.396 | 448.199 | 1.044.824 | |
|
| ||||||||||||||||||
Totaal uitgaven stand ontwerpbegroting 2013 HWN |
|
| 2.728.863 | 3.072.135 | 2.157.605 | 2.871.423 | 2.466.135 | 2.266.296 | 2.900.973 | 3.282.342 | 2.200.462 | 2.308.124 | 1.949.571 | 1.768.654 | 1.298.333 | 1.238.570 | 1.177.854 | 1.167.362 | |
Totaal uitgaven stand eerste suppletoire wet 2013 HWN |
|
| 2.574.830 | 2.957.827 | 2.086.006 | 2.201.928 | 2.318.111 | 2.290.347 | 2.879.688 | 3.558.338 | 2.188.211 | 2.569.808 | 2.317.028 | 2.267.036 | 2.069.777 | 2.002.650 | 1.959.587 | 2.065.826 | |
Totaal uitgaven stand Miljoenennota 2014 HWN |
|
| 2.494.262 | 2.800.084 | 2.128.842 | 1.756.603 | 2.291.915 | 2.241.331 | 2.916.274 | 3.427.133 | 2.331.692 | 2.707.003 | 2.487.667 | 2.431.671 | 2.238.103 | 2.112.909 | 2.048.722 | 2.154.677 | |
Ontwerpbegroting 2013 artikelonderdeel 12.09 Ontvangsten HWN |
|
| 262.105 | 182.021 | 57.577 | 490.329 | 112.698 | 33.050 | 33.050 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
Mutaties voorjaarsnota 2013 |
|
| – 134.654 | – 18.901 | 36.034 | – 350.682 | 29.386 | 89.868 | – 1.692 | 286.076 | 0 | 35.000 | 0 | 0 | 0 | 0 | 0 | 0 | |
Stand eerste suppletoire wet 2013 artikelonderdeel 12.09 Ontvangsten HWN |
|
| 127.451 | 163.120 | 93.611 | 139.647 | 142.084 | 122.918 | 31.358 | 286.076 | 0 | 35.000 | 0 | 0 | 0 | 0 | 0 | 0 | |
Bijdrage Stadsgewest Haaglanden | desaldering | 100 | 100 | 1 | |||||||||||||||
Kasritme regiobijdrage | desaldering | 0 | – 29.281 | 209.281 | – 80.000 | – 100.000 | 21 | ||||||||||||
Mutaties Miljoenennota 2014 |
|
| 100 | – 29.281 | 209.281 | 0 | – 80.000 | – 100.000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
Stand ontwerpbegroting 2014 artikelonderdeel 12.09 Ontvangsten |
|
| 127.551 | 133.839 | 302.892 | 139.647 | 62.084 | 22.918 | 31.358 | 286.076 | 0 | 35.000 | 0 | 0 | 0 | 0 | 0 | 0 |
Artikel 12 Hoofdwegennet
-
1. Dit betreft de verwerking van een Beter Benutten opdracht van het Stadsgewest Haaglanden. Het gaat om de A13 Rijswijk-Ypenburg: verlengen opstelstrook.
-
2. IenM dekt in de ontwerpbegroting over 2014 het budgettaire probleem dat is ontstaan door het niet uitkeren van de prijsbijstelling uit de resterende Investeringsruimte per investeringsdomein. Er resteert dan een kasritmeprobleem. IenM lost dit uiterlijk bij ontwerpbegroting 2017 op, maar zo mogelijk eerder bij een eerstvolgende herijking van het Investeringsprogramma. Dit impliceert dat ex ante het risico wordt geaccepteerd dat ex post een kasoverschrijding van het Infrastructuurfonds optreedt van maximaal het minbedrag in het betreffende jaar. IenM zal er desalniettemin op sturen om binnen de aangepaste kasranden te blijven.
-
3. Dit betreft de volgende verschuivingen binnen artikel 12 Wegen tussen aanleg en de overige artikelonderdelen:
-
– De jaarlijkse bijdrage van het Directoraat Generaal Bereikbaarheid (DGB) aan RWS in de financiering van de Verkeersonderneming voor de periode 2012–2015;
-
– Een overboeking voor de juiste toedeling van de index 2012 aan overige maatregelen (van 12.02 naar 12.03);
-
– Per 1 juli 2012 is de geluidwetgeving voor rijkswegen gewijzigd en opgenomen in de Wet milieubeheer («SWUNG»). Als gevolg van deze wetswijziging moeten aanvullende beheer- en onderhoudskosten worden gemaakt om te kunnen blijven voldoen aan de vastgestelde geluidsproductieplafonds. Voor de periode 2017– 2028 zullen de bedragen nog nader worden «gehard».
-
-
4. In 2009 is heeft het ministerie van Financiën toestemming verleend om een deel van de vordering van RWS op IenM in een periode van 15 jaar af te betalen. Hiervoor is een 15-jarige kasreeks in de begroting opgenomen. Deze reeks is technisch opgenomen in artikel 12.02 (Beheer en Onderhoud). Deze bijdrage is echter niet voor Beheer en Onderhoud bedoeld. Voorgesteld wordt om de afbetalingsreeks op te nemen in artikel 18.08.02 (Overige netwerkoverstijgende kosten). De voorwaarden waaronder de betaling aan RWS plaatsvindt blijven onveranderd.
-
5. Deze mutatie betreft onderstaande verschuivingen over de diverse aanlegartikelen van het Infrastructuurfonds:
-
– De extra bijdrage voor de Rotterdamse baan voor regionale/lokale infrastructuur (artikel 14) wordt via een kasschuif met het project A4 Delft–Schiedam op artikel 12 (uit het aanbestedingvoordeel) naar voren gehaald. De extra bijdrage wordt gedekt binnen het programmabudget op Regionale/lokale infrastructuur;
-
– Op artikelonderdeel 17.01 Westerscheldetunnel wordt voor de jaren 2013/2014 nog circa € 0,3 mln aan claims voor nadeelcompensatie verwacht. Dit bedrag is sterk afhankelijk van de uitspraak van de Raad van State. Na 2014 worden geen claims meer verwacht. Het restant kan daarom worden overgeheveld naar de investeringsruimte op 12.07;
-
– Vanwege de verkenning seinoptimalisatie Amersfoort (als maatregel uit het regiopakket) wordt circa € 0,1 mln overgeboekt vanuit artikel 12 (Beter Benutten) naar artikel 13 Spoorwegen;
-
– In het kader van een teruggave van middelen voor Anders Betalen voor Mobiliteit projecten (ABvM) wordt een overboeking tussen de artikelen 14 en 12 in het fonds aangebracht;
-
– Een overboeking uit artikel 13 Planuitwerking naar artikel 12 voor realisatiekosten die worden voorzien bij het project Zuidas;
-
– Een budgetoverheveling vanuit artikel 12 (project A4 Burgerveen-Leiden) naar artikel 17 HSL voor het schadeschap A4-HSL.
-
-
6. Tussen de Begroting van hoofdstuk XII en dit artikel worden de volgende overboekingen aangebracht:
-
– Subsidieregeling Euro-VI (schone motoren vrachtwagens en bussen): voor 2013 wordt een bedrag van € 5 mln overgeheveld. De uitvoering van deze regeling wordt verantwoord op artikel 20 in de Begroting van hoofdstuk XII;
-
– Beter Benutten: vanuit artikel 12 Beter benutten vindt een overboeking plaats naar de Begroting van hoofdstuk XII voor programmakosten en externe inhuur door het verlengen van de projectduur (in totaal € 1,2 mln). Tevens worden vanuit de Begroting van hoofdstuk XII de in 2012 onbesteed gebleven gelden voor Beter Benutten (circa € 0,8 mln) teruggeboekt naar artikel 12 in het infrastructuurfonds voor het in standhouden van het projecttotaal van Beter Benutten;
-
– Bijdrage van RWS (uit de artikelen 12, 15 en 18) aan de opdracht PDOK aan het Kadaster en Geonovum voor de jaren 2013–2016 (bijna € 0,3 mln per jaar);
-
– Een overboeking naar het ministerie van BZK voor de elektronische publicatie van verkeersbesluiten (€ 0,1 mln) en een overboeking vanuit de Begroting van hoofdstuk XII (€ 0,9 mln) in dit kader.
-
-
14. Dit is de toevoeging aan het Infrastructuurfonds van het uitgekeerde deel van de loonbijstelling 2013. Het betreft de hogere uitgaven voor de werkgever aan ouderdoms- en nabestaandenpensioen en een stijging van de bijdrage in het kader van de Zorgverzekeringswet.
-
18. Bij het DBFM-contract (Design, Build, Finance & Maintain) voor het project N33 Assen–Zuidbroek heeft de «financial close» plaatsgevonden, dit is budgettair verwerkt. Op verzoek van het Ministerie van Financiën wordt hier een proef uitgevoerd waarbij inflatiegerelateerde vergoedingen wordt uitbetaald. Een consequentie van deze proef is dat de mijlpaalvergoeding binnen het contract gemaximaliseerd is op 5 procent van de investeringssom.
-
19. MJPO: Het programma loopt af na 2018. Het resterende budget is overgeheveld naar de investeringsruimte van wegen (12.07).
-
20. Bij het DBFM-contract voor het project A1/A6 Schiphol Amsterdam Almere heeft de «financial close» plaatsgevonden, dit is budgettair verwerkt.
-
21. Dit betreft een aanpassing van kasritme van de regionale bijdragen aan de projecten A12/A15 Ressen–Oudbroeken en N35 Zwolle–Wijthmen.
-
22. Dit betreft een mutatie op basis van een actualisatie door RWS en beleid, rekening houdend met nieuwe planningsinformatie van RWS.
-
23. Dit betreft de administratieve verwerking van de wijzigingen in de budgetten van A4 Delft Schiedam en A10 2e Coentunnel.
-
24. Met deze schuif worden de kasreeksen voor de wegenprojecten Rotterdamsebaan en Verkeersruit Eindhoven (NOC) op begrotingsartikel 14 aangesloten bij de actuele planning.
-
25. Dit betreft het treffen van een reservering voor consequenties areaalgroei op beheer en onderhoud wegen onder planuitwerking vanuit de Investeringsruimte wegen en vanuit de bestaande reservering op artikel 18.12.
-
26. Bij A2 Holendrecht–Oudenrijn (Leidsche Rijn Tunnel) is in 1e suppletoire begroting 2013 € 56 mln toegevoegd aan het budget. Omdat slechts een beperkt deel nodig bleek, wordt bij deze begroting € 37 mln afgeboekt. Binnen de ZSM projecten is sprake van een meevaller (€ 32,3 mln).
Categorie | Totaal mutatie | 2013 | 2014 | 2015 | 2016 | 2017 | 2018 | 2019 | 2020 | 2021 | 2022 | 2023 | 2024 | 2025 | 2026 | 2027 | 2028 | Toelichting | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Ontwerpbegroting 2013 artikelonderdeel 13.02 Beheer, onderh.& verv. | 1.324.516 | 1.236.385 | 1.236.800 | 1.111.748 | 1.210.582 | 1.221.869 | 1.130.098 | 1.284.238 | 1.167.164 | 1.166.485 | 1.166.549 | 1.185.095 | 1.120.779 | 1.175.779 | 1.175.779 | 1.175.779 | |||
Mutaties voorjaarsnota 2013 | – 4.611 | 13.850 | – 11.348 | 24.486 | 20.717 | 84.117 | 3.611 | – 7.251 | 9.125 | 5.322 | – 6.978 | 29.251 | 86.246 | 41.896 | 43.085 | 2.344 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 13.02 Beheer, onderh.& verv. | 1.319.905 | 1.250.235 | 1.225.452 | 1.136.234 | 1.231.299 | 1.305.986 | 1.133.709 | 1.276.987 | 1.176.289 | 1.171.807 | 1.159.571 | 1.214.346 | 1.207.025 | 1.217.675 | 1.218.864 | 1.178.123 | |||
Indexering 2013 | Intens./extens. | 294.906 | 20.524 | 20.531 | 18.455 | 20.096 | 20.283 | 18.760 | 21.318 | 19.375 | 19.364 | 19.365 | 19.673 | 18.605 | 19.519 | 19.519 | 19.519 | 2 | |
Loonbijstelling 2013 | Intens./extens. | 11.626 | 927 | 768 | 762 | 608 | 740 | 711 | 711 | 711 | 711 | 711 | 711 | 711 | 711 | 711 | 711 | 711 | 14 |
Desaldering spoorwegen | desaldering | – 76.148 | – 8.651 | – 7.499 | – 7.499 | – 7.499 | – 7.500 | – 7.500 | – 7.500 | – 7.500 | – 7.500 | – 7.500 | 16 | ||||||
Mutaties Miljoenennota 2014 | – 7.724 | 13.793 | 13.794 | 11.564 | 13.336 | 13.494 | 11.971 | 14.529 | 12.586 | 12.575 | 20.076 | 20.384 | 19.316 | 20.230 | 20.230 | 20.230 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 13.02 Beheer, onderh.& verv. | 1.312.181 | 1.264.028 | 1.239.246 | 1.147.798 | 1.244.635 | 1.319.480 | 1.145.680 | 1.291.516 | 1.188.875 | 1.184.382 | 1.179.647 | 1.234.730 | 1.226.341 | 1.237.905 | 1.239.094 | 1.198.353 | |||
Ontwerpbegroting 2013 artikelonderdeel 13.03 Aanleg | 706.311 | 986.382 | 1.181.055 | 1.172.551 | 1.181.262 | 1.103.173 | 820.467 | 566.848 | 417.524 | 172.254 | 277.088 | 283.293 | 138.877 | 116.739 | 114.339 | 127.934 | |||
Mutaties voorjaarsnota 2013 | 152.876 | – 3.981 | – 46.463 | – 82.113 | – 116.641 | – 145.816 | 2.935 | 20.601 | – 22.614 | 125.638 | 220.841 | 188.542 | 323.288 | 392.716 | 348.322 | 279.318 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 13.03 Aanleg | 859.187 | 982.401 | 1.134.592 | 1.090.438 | 1.064.621 | 957.357 | 823.402 | 587.449 | 394.910 | 297.892 | 497.929 | 471.835 | 462.165 | 509.455 | 462.661 | 407.252 | |||
Overboeking binnen Infrastructuurfonds | Intens./extens. | – 12.084 | – 37.084 | 7.000 | 18.000 | 5 | |||||||||||||
Overboeking binnen artikel 13 | neutraal | – 66.404 | 6.322 | 5.000 | 15.821 | 70.000 | 62.000 | 240 | 651 | –226.438 | 8 | ||||||||
Overboeking HXII – IF artikel 13 | Intens./extens. | – 11.400 | – 2.500 | – 2.900 | – 6.000 | 9 | |||||||||||||
Desaldering spoorwegen | desaldering | 62.712 | 54.094 | 612 | 306 | 800 | 800 | 1.070 | 1.070 | 2.140 | 1.820 | 16 | |||||||
Overboeking binnen artikel 13 | neutraal | 6 | 0 | 1 | 0 | 3 | – 1 | 1 | 1 | 7.865 | 1.741 | – 253 | 92 | –9.444 | 17 | ||||
Mutaties Miljoenennota 2014 | 20.832 | – 2.287 | 6.306 | 33.824 | 70.799 | 62.800 | 1.071 | 1.310 | 2.792 | 1.820 | 0 | 7.865 | 1.741 | – 253 | 92 | –235.882 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 13.03 Aanleg | 880.019 | 980.114 | 1.140.898 | 1.124.262 | 1.135.420 | 1.020.157 | 824.473 | 588.759 | 397.702 | 299.712 | 497.929 | 479.700 | 463.906 | 509.202 | 462.753 | 171.370 | |||
Ontwerpbegroting 2013 artikelonderdeel 13.04 GIV/PPS | 148.776 | 148.040 | 148.099 | 148.580 | 148.790 | 149.422 | 152.578 | 161.354 | 162.228 | 163.666 | 164.985 | 166.604 | 167.547 | 168.015 | 166.165 | 150.047 | |||
Mutaties voorjaarsnota 2013 | – 8.583 | – 2.452 | 15.497 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 2.449 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 13.04 GIV/PPS | 140.193 | 145.588 | 163.596 | 148.580 | 148.790 | 149.422 | 152.578 | 161.354 | 162.228 | 163.666 | 164.985 | 166.604 | 167.547 | 168.015 | 166.165 | 152.496 | |||
Mutaties Miljoenennota 2014 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | , | ||
Stand ontwerpbegroting 2014 artikelonderdeel 13.04 GIV/PPS | 140.193 | 145.588 | 163.596 | 148.580 | 148.790 | 149.422 | 152.578 | 161.354 | 162.228 | 163.666 | 164.985 | 166.604 | 167.547 | 168.015 | 166.165 | 152.496 | |||
Ontwerpbegroting 2013 artikelonderdeel 13.05 Verk.& Planuitw. | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties voorjaarsnota 2013 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 13.05 Verk.& Planuitw. | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties Miljoenennota 2014 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 13.05 Verk.& Planuitw. | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Ontwerpbegroting 2013 artikelonderdeel 13.07 Rente & afl. | 18.150 | 18.150 | 18.150 | 18.150 | 18.150 | 18.150 | 18.150 | 18.150 | 18.150 | 18.150 | 18.150 | 18.150 | 18.150 | 18.150 | 18.150 | 18.150 | |||
Mutaties voorjaarsnota 2013 | 30.247 | – 1.553 | – 1.553 | – 1.553 | – 1.553 | – 1.553 | – 1.553 | – 1.553 | – 1.553 | – 1.553 | – 1.553 | – 1.553 | – 1.553 | – 1.553 | – 1.553 | –1.553 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 13.07 Rente & afl. | 48.397 | 16.597 | 16.597 | 16.597 | 16.597 | 16.597 | 16.597 | 16.597 | 16.597 | 16.597 | 16.597 | 16.597 | 16.597 | 16.597 | 16.597 | 16.597 | |||
Mutaties Miljoenennota 2014 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 13.07 Rente & afl. | 48.397 | 16.597 | 16.597 | 16.597 | 16.597 | 16.597 | 16.597 | 16.597 | 16.597 | 16.597 | 16.597 | 16.597 | 16.597 | 16.597 | 16.597 | 16.597 | |||
Ontwerpbegroting 2013 artikelonderdeel 13.08 Investeringsruimte | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties voorjaarsnota 2013 | 23 | 10.000 | 20.000 | 40.000 | 80.000 | 62.000 | 25.000 | 25.241 | 52.655 | 50.500 | 52.000 | 126.552 | 98.528 | 69.035 | 141.127 | 323.515 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 13.08 Investeringsruimte | 23 | 10.000 | 20.000 | 40.000 | 80.000 | 62.000 | 25.000 | 25.241 | 52.655 | 50.500 | 52.000 | 126.552 | 98.528 | 69.035 | 141.127 | 323.515 | |||
Indexering 2013 | Intens./extens. | – 294.906 | 0 | – 20.524 | – 20.531 | – 18.455 | – 20.096 | – 20.283 | – 18.760 | – 21.318 | – 19.375 | – 19.364 | – 19.365 | – 19.673 | – 18.605 | – 19.519 | – 19.519 | –19.519 | 2 |
Overboeking binnen artikel 13 | neutraal | 66.408 | – 6.320 | – 4.998 | – 15.821 | – 70.000 | – 62.000 | – 240 | – 651 | 226.438 | 8 | ||||||||
Desaldering spoorwegen | desaldering | 92.266 | 6.299 | 2.137 | 5.983 | 5.983 | 5.568 | 5.894 | 5.847 | 6.063 | 5.203 | 5.637 | 7.567 | 7.585 | 5.625 | 5.625 | 5.625 | 5.625 | 16 |
Overboeking binnen artikel 13 | neutraal | – 6 | – 2 | – 1 | 2 | – 3 | 1 | – 1 | – 1 | – 7.865 | – 1.741 | 253 | – 92 | 9.444 | 17 | ||||
Mutaties Miljoenennota 2014 | – 23 | – 18.388 | – 19.544 | – 28.296 | – 84.527 | – 76.389 | – 12.914 | – 15.495 | – 14.824 | – 13.727 | – 11.798 | – 19.953 | – 14.721 | – 13.641 | – 13.986 | 221.988 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 13.08 Investeringsruimte | 0 | – 8.388 | 456 | 11.704 | – 4.527 | – 14.389 | 12.086 | 9.746 | 37.831 | 36.773 | 40.202 | 106.599 | 83.807 | 55.394 | 127.141 | 545.503 | |||
Totaal uitgaven stand ontwerpbegroting 2013 Spoorwegen | 2.197.753 | 2.388.957 | 2.584.104 | 2.451.029 | 2.558.784 | 2.492.614 | 2.121.293 | 2.030.590 | 1.765.066 | 1.520.555 | 1.626.772 | 1.653.142 | 1.445.353 | 1.478.683 | 1.474.433 | 1.471.910 | |||
Totaal uitgaven stand eerste suppletoire wet 2013 Spoorwegen | 2.367.705 | 2.404.821 | 2.560.237 | 2.431.849 | 2.541.307 | 2.491.362 | 2.151.286 | 2.067.628 | 1.802.679 | 1.700.462 | 1.891.082 | 1.995.934 | 1.951.862 | 1.980.777 | 2.005.414 | 2.077.982 | |||
Totaal uitgaven stand Miljoenennota 2014 Spoorwegen | 2.380.790 | 2.397.939 | 2.560.793 | 2.448.941 | 2.540.915 | 2.491.267 | 2.151.414 | 2.067.972 | 1.803.233 | 1.701.130 | 1.899.360 | 2.004.230 | 1.958.198 | 1.987.113 | 2.011.750 | 2.084.318 | |||
Ontwerpbegroting 2013 artikelonderdeel 13.09 Ontvangsten spoorw. | 60.000 | 59.999 | 237.999 | 181.999 | 194.208 | 195.315 | 199.492 | 203.541 | 207.468 | 209.601 | 211.665 | 211.988 | 175.300 | 175.300 | 175.300 | 175.300 | |||
Mutaties voorjaarsnota 2013 | 112.581 | 10.000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 13.09 Ontvangsten spoorw. | 172.581 | 69.999 | 237.999 | 181.999 | 194.208 | 195.315 | 199.492 | 203.541 | 207.468 | 209.601 | 211.665 | 211.988 | 175.300 | 175.300 | 175.300 | 175.300 | |||
Desaldering spoorwegen | desaldering | 78.830 | 51.742 | – 4.750 | – 1.210 | – 1.516 | – 1.132 | – 806 | – 583 | – 367 | – 157 | – 43 | 7.567 | 7.585 | 5.625 | 5.625 | 5.625 | 5.625 | 16 |
Mutaties Miljoenennota 2014 | 51.742 | – 4.750 | – 1.210 | – 1.516 | – 1.132 | – 806 | – 583 | – 367 | – 157 | – 43 | 7.567 | 7.585 | 5.625 | 5.625 | 5.625 | 5.625 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 13.09 Ontvangsten spoorw. | 224.323 | 65.249 | 236.789 | 180.483 | 193.076 | 194.509 | 198.909 | 203.174 | 207.311 | 209.558 | 219.232 | 219.573 | 180.925 | 180.925 | 180.925 | 180.925 |
Artikel 13 Spoorwegen
-
2. IenM dekt in de ontwerpbegroting over 2014 het budgettaire probleem dat is ontstaan door het niet uitkeren van de prijsbijstelling uit de resterende Investeringsruimte per investeringsdomein. Er resteert dan een kasritmeprobleem. IenM lost dit uiterlijk bij ontwerpbegroting 2017 op, maar zo mogelijk eerder bij een eerstvolgende herijking van het Investeringsprogramma. Dit impliceert dat ex ante het risico wordt geaccepteerd dat ex post een kasoverschrijding van het Infrastructuurfonds optreedt van maximaal het minbedrag in het betreffende jaar. IenM zal er desalniettemin op sturen om binnen de aangepaste kasranden te blijven.
-
5. Deze mutatie betreft onderstaande verschuivingen over de diverse aanlegartikelen van het Infrastructuurfonds:
-
– Vanwege de verkenning seinoptimalisatie Amsersvoort (als maatregel uit het regiopakket) wordt circa € 0,1 mln overgeboekt vanuit artikel 12 (Beter Benutten) naar artikel 13 Spoorwegen;
-
– Een overboeking vanuit artikel 13 (Afdekking risico's spoorprogramma's) naar artikel 17 voor de financiering van de pilot geluidsmaatregelen Lansingerland. Dit in lijn met de voortgangsinformatie die eerder aan de Tweede Kamer is gezonden (Voortgangsrapportage 31 HSL);
-
– Voor de realisatie op het project Utrecht Uithof heeft de regio Utrecht al een aanzienlijk bedrag voorgefinancierd. IenM heeft eerder richting regio Utrecht aangegeven niet eerder dan in 2016 middelen beschikbaar te hebben om deze uitgaven te compenseren maar wel te zullen bezien of er mogelijkheden zijn om eerder tot betaling over te gaan. Die zijn er thans op artikel 13 Spoorwegen waar de AP (Aanvullende Post) gelden voor 2013 dit jaar nog niet tot betalingen leiden;
-
– Een overboeking uit artikel 13 PUV naar artikel 12 voor realisatiekosten die worden voorzien bij het project Zuidas;
-
– Afrekening Hollandse Brug OV SAAL-RRAAM: Met betrekking tot de Hollandse brug variant in relatie tot OV SAAL MT is afgesproken dat van het geraamde budget ad circa € 1,8 mln OV SAAL 2/3 voor haar rekening neemt (Infrastructuurfonds begrotingsartikel 13) en RRAAM 1/3 (Infrastructuurfonds begrotingsartikel 18). De totale realisatie bedraagt uiteindelijk € 1,7 mln. Volgens de verdeelsleutel vindt een budgettaire compensatie plaats van afgerond € 495.000,- vanuit OV SAAL naar RRAAM.
-
-
8. Deze mutatie betreft onderstaande verschuivingen binnen artikel 13 Spoorwegen tussen aanleg en de overige artikelonderdelen;
-
– In het BO MIRT najaar 2012 is geconstateerd dat de Calandbrug in de Betuweroute/Havenspoorlijn zonder levensverlengende maatregelen rond 2020 aan het einde van haar levensduur is. Op 3 april 2013 hebben het Havenbedrijf Rotterdam en de Staat een overeenkomst ondertekend waarbij de Staat toezegt in mei een startbeslissing te nemen inzake een verkenning problematiek Calandspoorbrug. In deze overeenkomst heeft IenM zich gebonden aan grootschalige renovatie van de Calandspoorbrug voor 2019 ad € 157 mln;
-
– De verwerking van de scope-uitbreiding PHS: dak 7e perron;
-
– De verwerking van de wijzigingsbeschikking 2013 met betrekking tot gereedgekomen lijnen/halte van lopende projecten;
-
– Een kasschuif tussen de artikelonderdelen 13.03 en 13.08 om de Investeringsruimte in 2013 naar latere jaren te plaatsen. Dit jaar worden daaruit geen uitgaven meer voorzien.
-
-
9. Uit dit artikelonderdeel worden de volgende overboekingen naar de begroting van HXII aangebracht voor:
-
– Gelden voor het onderzoek Roadmap ERTMS (€ 2,5 mln);
-
– De BDU voor de verlenging Spoorlijn van Roodeschool naar Eemshaven (€ 2,9 mln).
-
-
14. Dit is de toevoeging aan het Infrastructuurfonds van het uitgekeerde deel van de loonbijstelling 2013. Het betreft de hogere uitgaven voor de werkgever aan ouderdoms- en nabestaandenpensioen en een stijging van de bijdrage in het kader van de Zorgverzekeringswet.
-
16. Deze desaldering (uitgaven/ontvangsten) betreft:
-
– De verwerking van de Boete NS (€ 2,8 mln);
-
– De reisinformatie is door ProRail overgedragen aan de NS. De reisinformatie wordt verankerd in de Vervoerconcessie en structureel verrekend met de concessievergoeding (€ 7,5 mln per jaar);
-
– Indexering concessievergoeding naar prijspeil 2013 (circa € 6 mln per jaar) naar het huidige prijspeilniveau;
-
– Een bijdrage van de provincie Gelderland aan het project Quick scan Decentraal Spoor Gelderland ad € 1,5 mln voor het project «Vrijleggen treindienst Zutphen–Winterswijk te Zutphen».
-
-
17. Met deze kasschuif wordt zoveel mogelijk aangesloten bij de actuele inzichten in de programmering.
Categorie | Totaal mutatie | 2013 | 2014 | 2015 | 2016 | 2017 | 2018 | 2019 | 2020 | 2021 | 2022 | 2023 | 2024 | 2025 | 2026 | 2027 | 2028 | Toelichting | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Ontwerpbegroting 2013 artikelonderdeel 14.01 Grote reg./lok.proj. | 60.771 | 104.830 | 99.343 | 44.156 | 235.601 | 218.604 | 116.825 | 39.129 | 143.539 | 143.500 | 143.506 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties voorjaarsnota 2013 | 539 | –17.794 | –26.055 | 102.501 | –24.429 | –15.385 | –10.461 | –9.280 | –10.035 | 22.299 | 41.611 | 59.568 | 97.027 | 96.017 | 99.443 | 132.427 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 14.01 Grote reg./lok.proj. | 61.310 | 87.036 | 73.288 | 146.657 | 211.172 | 203.219 | 106.364 | 29.849 | 133.504 | 165.799 | 185.117 | 59.568 | 97.027 | 96.017 | 99.443 | 132.427 | |||
Indexering 2013 | Intens./extens. | – 854 | – 1 | – 531 | – 74 | – 67 | – 45 | – 45 | – 70 | – 21 | 2 | ||||||||
Overboeking binnen Infrastructuurfonds | Intens./extens. | – 3.733 | 25.000 | – 2.439 | – 8.294 | – 18.000 | 63.500 | – 63.500 | 5 | ||||||||||
Overboeking HXII – IF artikel 14 | Intens./extens. | – 7.262 | – 2.500 | – 4.762 | 11 | ||||||||||||||
Leenconstructie wegen–reg/lok. | Intens./extens. | 0 | 5.686 | 173.268 | 32.753 | – 24.581 | – 63.858 | – 49.203 | – 52.828 | – 21.237 | 24 | ||||||||
Mutaties Miljoenennota 2014 | 24.999 | – 5.470 | – 8.368 | – 22.829 | 63.455 | – 45 | 5.616 | 173.247 | – 30.747 | – 24.581 | – 63.858 | – 49.203 | – 52.828 | – 21.237 | 0 | 0 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 14.01 Grote reg./lok.proj. | 86.309 | 81.566 | 64.920 | 123.828 | 274.627 | 203.174 | 111.980 | 203.096 | 102.757 | 141.218 | 121.259 | 10.365 | 44.199 | 74.780 | 99.443 | 132.427 | |||
Ontwerpbegroting 2013 artikelonderdeel 14.02 Reg.Mob.fonds. | 30.257 | 12.750 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties voorjaarsnota 2013 | – 3.654 | 242 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 14.02 Reg.Mob.fonds. | 26.603 | 12.992 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties Miljoenennota 2014 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 14.02 Reg.Mob.fonds. | 26.603 | 12.992 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Ontwerpbegroting 2013 artikelonderdeel 14.03 RSP/ZZL | 44.955 | 144.149 | 54.009 | 212.450 | 163.286 | 136.631 | 116.631 | 39.693 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties voorjaarsnota 2013 | – 1.370 | 2.731 | 1.023 | 4.025 | 3.093 | 2.588 | 2.210 | 752 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 14.03 RSP/ZZL | 43.585 | 146.880 | 55.032 | 216.475 | 166.379 | 139.219 | 118.841 | 40.445 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Indexering 2013 | Intens./extens. | 854 | 1 | 531 | 74 | 67 | 45 | 45 | 70 | 21 | 2 | ||||||||
Mutaties Miljoenennota 2014 | 1 | 531 | 74 | 67 | 45 | 45 | 70 | 21 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 14.03 RSP/ZZL | 43.586 | 147.411 | 55.106 | 216.542 | 166.424 | 139.264 | 118.911 | 40.466 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Totaal uitgaven stand ontwerpbegroting 2013 Reg./Lok.infra. | 135.983 | 261.729 | 153.352 | 256.606 | 398.887 | 355.235 | 233.456 | 78.822 | 143.539 | 143.500 | 143.506 | 0 | 0 | 0 | 0 | 0 | |||
Totaal uitgaven stand eerste suppletoire wet 2013 Reg./Lok.infra. | 131.498 | 246.908 | 128.320 | 363.132 | 377.551 | 342.438 | 225.205 | 70.294 | 133.504 | 165.799 | 185.117 | 59.568 | 97.027 | 96.017 | 99.443 | 132.427 | |||
Totaal uitgaven stand Miljoenennota 2014 Reg./Lok.infra. | 156.498 | 241.969 | 120.026 | 340.370 | 441.051 | 342.438 | 230.891 | 243.562 | 102.757 | 141.218 | 121.259 | 10.365 | 44.199 | 74.780 | 99.443 | 132.427 | |||
Ontwerpbegroting 2013 artikelonderdeel 14.09 Ontvangsten | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties voorjaarsnota 2013 | 600 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 14.09 Ontvangsten Reg./lok.infra | 600 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties Miljoenennota 2014 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 14.09 Ontvangsten Reg./lok.infra | 600 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Artikel 14 Regionaal, lokale infrastructuur
-
2. IenM dekt in de ontwerpbegroting over 2014 het budgettaire probleem dat is ontstaan door het niet uitkeren van de prijsbijstelling uit de resterende Investeringsruimte per investeringsdomein. Er resteert dan een kasritmeprobleem. IenM lost dit uiterlijk bij ontwerpbegroting 2017 op, maar zo mogelijk eerder bij een eerstvolgende herijking van het Investeringsprogramma. Dit impliceert dat ex ante het risico wordt geaccepteerd dat ex post een kasoverschrijding van het Infrastructuurfonds optreedt van maximaal het minbedrag in het betreffende jaar. IenM zal er desalniettemin op sturen om binnen de aangepaste kasranden te blijven.
-
5. Deze mutatie betreft onderstaande verschuivingen over de diverse aanlegartikelen van het Infrastructuurfonds:
-
– De extra bijdrage voor de Rotterdamsebaan voor regionale/lokale infrastructuur (artikel 14) wordt via een kasschuif met het project A4 Delft–Schiedam op artikel 12 (uit het aanbestedingvoordeel) naar voren gehaald. De extra bijdrage wordt gedekt binnen het programmabudget op Regionale/lokale infrastructuur;
-
– Voor de realisatie van het project Utrecht Uithof heeft de regio Utrecht al een aanzienlijk bedrag voorgefinancierd. IenM heeft eerder richting regio Utrecht aangegeven niet eerder dan in 2016 middelen beschikbaar te hebben om deze uitgaven te compenseren maar wel te zullen bezien of er mogelijkheden zijn om eerder tot betaling over te gaan. Die zijn er thans op artikel 13 Spoorwegen waar de middelen uit het Begrotingsakkoord (Aanvullende Post OV) voor 2013 dit jaar nog niet tot betalingen leiden;
-
– Door een teruggave van middelen voor Anders Betalen voor Mobiliteit projecten (ABvM) wordt een overboeking tussen de artikelen 14 en 12 in het fonds aangebracht.
-
-
11. De BDU voor het jaar 2013 is in december 2012 vastgesteld. Daarin is overeenkomstig de gebruikelijke werkwijze een forfaitaire index opgenomen. Vanuit artikel 14 Regionaal/lokale infrastructuur wordt dekking geboden voor het niet uitkeren van de prijsindex en overgeboekt naar de begroting van HXII.
-
24. Met deze schuif worden de kasreeksen voor de wegenprojecten Rotterdamsebaan en Verkeersruit Eindhoven (NOC) op begrotingsartikel 14 aangesloten bij de actuele planning.
Categorie | Totaal mutatie | 2013 | 2014 | 2015 | 2016 | 2017 | 2018 | 2019 | 2020 | 2021 | 2022 | 2023 | 2024 | 2025 | 2026 | 2027 | 2028 | Toelichting | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Ontwerpbegroting 2013 artikelonderdeel 15.01 Verkeersmgmt. | 12.770 | 13.336 | 11.803 | 12.652 | 12.651 | 12.651 | 12.651 | 12.651 | 12.651 | 12.651 | 12.651 | 12.672 | 12.672 | 12.672 | 12.672 | 12.672 | |||
Mutaties voorjaarsnota 2013 | 728 | 257 | 260 | 256 | 257 | 257 | 257 | 257 | 268 | 268 | 268 | 247 | 247 | 247 | 247 | 247 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 15.01 Verkeersmgmt. | 13.498 | 13.593 | 12.063 | 12.908 | 12.908 | 12.908 | 12.908 | 12.908 | 12.919 | 12.919 | 12.919 | 12.919 | 12.919 | 12.919 | 12.919 | 12.919 | |||
Indexering 2013 | Intens./extens. | 3.432 | 224 | 226 | 200 | 214 | 214 | 214 | 214 | 214 | 214 | 214 | 214 | 214 | 214 | 214 | 214 | 214 | 2 |
Mutaties Miljoenennota 2014 | 224 | 226 | 200 | 214 | 214 | 214 | 214 | 214 | 214 | 214 | 214 | 214 | 214 | 214 | 214 | 214 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 15.01 Verkeersmgmt. | 13.722 | 13.819 | 12.263 | 13.122 | 13.122 | 13.122 | 13.122 | 13.122 | 13.133 | 13.133 | 13.133 | 13.133 | 13.133 | 13.133 | 13.133 | 13.133 | |||
Ontwerpbegroting 2013 artikelonderdeel 15.02 Beheer, onderh.& verv. | 298.884 | 284.762 | 260.627 | 275.898 | 190.100 | 217.125 | 173.580 | 215.854 | 218.056 | 253.356 | 277.795 | 271.826 | 271.826 | 274.326 | 277.011 | 266.085 | |||
Mutaties voorjaarsnota 2013 | 4.028 | 72.772 | 108.264 | 42.457 | 63.207 | – 2.034 | 39.272 | 5.164 | 20.614 | – 9.971 | – 34.653 | – 8.684 | – 37.684 | – 40.184 | – 44.774 | – 39.555 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 15.02 Beheer, onderh.& verv. | 302.912 | 357.534 | 368.891 | 318.355 | 253.307 | 215.091 | 212.852 | 221.018 | 238.670 | 243.385 | 243.142 | 263.142 | 234.142 | 234.142 | 232.237 | 226.530 | |||
Indexering 2013 | Intens./extens. | 68.659 | 5.025 | 5.931 | 6.121 | 5.862 | 3.622 | 3.568 | 3.532 | 3.667 | 3.948 | 3.971 | 4.013 | 4.002 | 3.943 | 3.928 | 3.727 | 3.799 | 2 |
Baltic Ace | Intens./extens. | 77.000 | 39.000 | 38.000 | 26 | ||||||||||||||
Mutaties Miljoenennota 2014 | 5.025 | 44.931 | 44.121 | 5.862 | 3.622 | 3.568 | 3.532 | 3.667 | 3.948 | 3.971 | 4.013 | 4.002 | 3.943 | 3.928 | 3.727 | 3.799 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 15.02 Beheer, onderh.& verv. | 307.937 | 402.465 | 413.012 | 324.217 | 256.929 | 218.659 | 216.384 | 224.685 | 242.618 | 247.356 | 247.155 | 267.144 | 238.085 | 238.070 | 235.964 | 230.329 | |||
Ontwerpbegroting 2013 artikelonderdeel 15.03 Aanleg | 284.743 | 339.668 | 289.951 | 218.654 | 242.753 | 197.684 | 224.570 | 61.754 | 229.774 | 159.343 | 126.548 | 85.074 | 198.074 | 238.074 | 253.568 | 10.142 | |||
Mutaties voorjaarsnota 2013 | 46.467 | – 53.656 | – 120.411 | – 36.055 | – 65.648 | – 6.458 | – 41.166 | – 5.757 | – 24.647 | 37.042 | 80.216 | 5.623 | 97.313 | 119.109 | 39.070 | 36.276 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 15.03 Aanleg | 331.210 | 286.012 | 169.540 | 182.599 | 177.105 | 191.226 | 183.404 | 55.997 | 205.127 | 196.385 | 206.764 | 90.697 | 295.387 | 357.183 | 292.638 | 46.418 | |||
Indexering 2013 | Intens./extens. | 32.742 | 5.142 | 4.525 | 2.670 | 2.218 | 1.586 | 820 | 1.152 | 472 | 3.846 | 88 | 88 | 88 | 3.131 | 3.131 | 3.697 | 88 | 2 |
Overboeking binnen artikel 15 | neutraal | 23.345 | 24.000 | – 655 | 12 | ||||||||||||||
Overboeking HXII – IF artikel 15 | Intens./extens. | – 5.000 | – 5.000 | 15 | |||||||||||||||
Baltic Ace | Intens./extens. | 0 | – 39.000 | – 38.000 | 77.000 | 26 | |||||||||||||
Mutaties Miljoenennota 2014 | 142 | – 34.475 | – 35.330 | 2.218 | 1.586 | 820 | 1.152 | 472 | 80.846 | 88 | 88 | 88 | 3.131 | 3.131 | 27.697 | – 567 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 15.03 Aanleg | 331.352 | 251.537 | 134.210 | 184.817 | 178.691 | 192.046 | 184.556 | 56.469 | 285.973 | 196.473 | 206.852 | 90.785 | 298.518 | 360.314 | 320.335 | 45.851 | |||
Ontwerpbegroting 2013 artikelonderdeel 15.05 Verk.& Planuitw. voor tracebesl. | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties voorjaarsnota 2013 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 15.05 Verk.& Planuitw. voor tracebesl. | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties Miljoenennota 2014 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 15.05 Verk.& Planuitw. voor tracebesl. | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Ontwerpbegroting 2013 artikelonderdeel 15.06 Netwerk HVWN | 247.723 | 234.036 | 224.847 | 222.822 | 220.998 | 219.440 | 219.284 | 219.240 | 221.402 | 221.402 | 221.402 | 221.777 | 221.777 | 221.777 | 221.777 | 221.777 | |||
Mutaties voorjaarsnota 2013 | 3.929 | 1.994 | 1.937 | 1.923 | 1.912 | 1.901 | 1.900 | 1.899 | 1.995 | 2.237 | 2.370 | 2.493 | 2.751 | 2.744 | 2.768 | 1.960 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 15.06 Netwerk HVWN | 251.652 | 236.030 | 226.784 | 224.745 | 222.910 | 221.341 | 221.184 | 221.139 | 223.397 | 223.639 | 223.772 | 224.270 | 224.528 | 224.521 | 224.545 | 223.737 | |||
Indexering 2013 | Intens./extens. | 3.530 | 215 | 229 | 217 | 218 | 218 | 218 | 218 | 218 | 218 | 218 | 218 | 225 | 225 | 225 | 225 | 225 | 2 |
Loonbijstelling 2013 | Intens./extens. | 3.594 | 252 | 236 | 227 | 225 | 223 | 221 | 221 | 221 | 221 | 221 | 221 | 221 | 221 | 221 | 221 | 221 | 14 |
Overboeking HXII – IF artikel 15 | Intens./extens. | 5.457 | 3.238 | 2.298 | – 37 | – 42 | 15 | ||||||||||||
Mutaties Miljoenennota 2014 | 3.705 | 2.763 | 407 | 401 | 441 | 439 | 439 | 439 | 439 | 439 | 439 | 446 | 446 | 446 | 446 | 446 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 15.06 Netwerk HVWN | 255.357 | 238.793 | 227.191 | 225.146 | 223.351 | 221.780 | 221.623 | 221.578 | 223.836 | 224.078 | 224.211 | 224.716 | 224.974 | 224.967 | 224.991 | 224.183 | |||
Ontwerpbegroting 2013 artikelonderdeel 15.07 Investeringsruimte HVWN | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties voorjaarsnota 2013 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 65.839 | 39.018 | 18.755 | 100.082 | 137.186 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 15.07 Investeringsruimte HVWN | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 65.839 | 39.018 | 18.755 | 100.082 | 137.186 | |||
Indexering 2013 | Intens./extens. | – 113.752 | – 11.848 | – 11.451 | – 9.724 | – 8.784 | – 5.888 | – 5.062 | – 5.297 | – 4.853 | – 8.611 | – 4.743 | – 4.735 | – 4.734 | – 7.718 | – 7.703 | – 8.017 | – 4.584 | 2 |
Overboeking binnen artikel 15 | neutraal | – 23.345 | – 24.000 | 655 | 12 | ||||||||||||||
Mutaties Miljoenennota 2014 | – 11.848 | – 11.451 | – 9.724 | – 8.784 | – 5.888 | – 5.062 | – 5.297 | – 4.853 | – 8.611 | – 4.743 | – 4.735 | – 4.734 | – 7.718 | – 7.703 | – 32.017 | – 3.929 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 15.07 Investeringsruimte HVWN | – 11.848 | – 11.451 | – 9.724 | – 8.784 | – 5.888 | – 5.062 | – 5.297 | – 4.853 | – 8.611 | – 4.743 | -4.735 | 61.105 | 31.300 | 11.052 | 68.065 | 133.257 | |||
Totaal uitgaven stand ontwerpbegroting 2013 HVWN | 844.120 | 871.802 | 787.228 | 730.026 | 666.502 | 646.900 | 630.085 | 509.499 | 681.883 | 646.752 | 638.396 | 591.349 | 704.349 | 746.849 | 765.028 | 510.676 | |||
Totaal uitgaven stand eerste suppletoire wet 2013 HVWN | 899.272 | 893.169 | 777.278 | 738.607 | 666.230 | 640.566 | 630.348 | 511.062 | 680.113 | 676.328 | 686.597 | 656.867 | 805.994 | 847.520 | 862.421 | 646.790 | |||
Totaal uitgaven stand Miljoenennota 2014 HVWN | 896.520 | 895.163 | 776.952 | 738.518 | 666.205 | 640.545 | 630.388 | 511.001 | 756.949 | 676.297 | 686.616 | 656.883 | 806.010 | 847.536 | 862.488 | 646.753 | |||
Ontwerpbegroting 2013 artikelonderdeel 15.09 Ontvangsten HVWN | 30.036 | 22.155 | 4.444 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties voorjaarsnota 2013 | 9.174 | 9.958 | 2.232 | 7.530 | 14.510 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 15.09 Ontvangsten HVWN | 39.210 | 32.113 | 6.676 | 7.530 | 14.510 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties Miljoenennota 2014 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 15.09 Ontvangsten HVWN | 39.210 | 32.113 | 6.676 | 7.530 | 14.510 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Artikel 15 Hoofdvaarwegennet
-
2. IenM dekt in de ontwerpbegroting over 2014 het budgettaire probleem dat is ontstaan door het niet uitkeren van de prijsbijstelling uit de resterende Investeringsruimte per investeringsdomein. Er resteert dan een kasritmeprobleem. IenM lost dit uiterlijk bij ontwerpbegroting 2017 op, maar zo mogelijk eerder bij een eerstvolgende herijking van het Investeringsprogramma. Dit impliceert dat ex ante het risico wordt geaccepteerd dat ex post een kasoverschrijding van het Infrastructuurfonds optreedt van maximaal het minbedrag in het betreffende jaar. IenM zal er desalniettemin op sturen om binnen de aangepaste kasranden te blijven.
-
12. Dit betreft de volgende verschuivingen binnen artikel 15 Vaarwegen tussen aanleg en de overige artikelonderdelen:
-
– Risicoreservering BTW Zeetoegang IJmond: In het recente verleden konden regionale partijen bij cofinanciering ten behoeve van bedrijfsmatige activiteiten in sommige gevallen BTW-vrijstelling via Financiën krijgen. Indien dit niet doorgaat bedraagt het rijksdeel in dit risico € 24 mln;
-
– Enkele relatief kleine bijstellingen/afrondingen.
-
-
14. Dit is de toevoeging aan het Infrastructuurfonds van het uitgekeerde deel van de loonbijstelling 2013. Het betreft de hogere uitgaven voor de werkgever aan ouderdoms- en nabestaandenpensioen en een stijging van de bijdrage in het kader van de Zorgverzekeringswet.
-
15. Via de decentralisatie-uitkering Binnenhavens ontvangt de gemeente Waalwijk € 4,6 mln. Deze gemeente kan de eventueel betaalde BTW terugvorderen via het BTW-compensatiefonds. De genoemde gemeente heeft een plan ingediend waarmee het landelijke netwerk van overslagvoorzieningen voor containervervoer over water wordt versterkt. De aanvraag voldoet hiermee aan de gestelde randvoorwaardelijke criteria. Via de begroting van HXII wordt daarom in totaal € 5 mln overgeboekt naar het Gemeente- en BTW Compensatiefonds.
Voorts wordt een bijdrage van RWS (uit de artikelen 12, 15 en 18) aan de opdracht PDOK aan het Kadaster en Geonovum voor de jaren 2013–2016 (bijna € 0,3 mln per jaar) alsmede een bijdrage voor Caribisch Nederland/BES voor investeringen in een Maritieme incidentenorganisatie (totaal € 6 mln) naar de begroting van HXII overgeboekt.
-
26. Op 5 december 2012 is de Baltic Ace na een aanvaring met de Corvus J gezonken in de vaarroute naar Rotterdam, 65 km ten westen van Goeree. Het scheepswrak bedreigt het mariene milieu en een vlot en veilig scheepvaartverkeer. Op dit gedeelte van de Noordzee is dit een verantwoordelijkheid van IenM/RWS. Dekking van de bergingskosten komt uit Vervanging en Renovaties in 2021.
Categorie | Totaal mutatie | 2013 | 2014 | 2015 | 2016 | 2017 | 2018 | 2019 | 2020 | 2021 | 2022 | 2023 | 2024 | 2025 | 2026 | 2027 | 2028 | Toelichting | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Ontwerpbegroting 2013 artikelonderdeel 17.01 W'scheldetunnel | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties voorjaarsnota 2013 | 4.804 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 17.01 W'scheldetunnel | 4.804 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Overboeking binnen Infrastructuurfonds | Intens./extens. | – 4.519 | – 4.519 | 5 | |||||||||||||||
Mutaties Miljoenennota 2014 | – 4.519 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 17.01 W'scheldetunnel | 285 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Ontwerpbegroting 2013 artikelonderdeel 17.02 Betuweroute | 4.699 | 6.000 | 6.000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties voorjaarsnota 2013 | 4.846 | 114 | 114 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 17.02 Betuweroute | 9.545 | 6.114 | 6.114 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties Miljoenennota 2014 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 17.02 Betuweroute | 9.545 | 6.114 | 6.114 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Ontwerpbegroting 2013 artikelonderdeel 17.03 HSL | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties voorjaarsnota 2013 | 8.294 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 17.03 HSL | 8.294 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Overboeking binnen Infrastructuurfonds | Intens./extens. | 12.060 | 11.742 | 159 | 159 | 5 | |||||||||||||
Mutaties Miljoenennota 2014 | 11.742 | 159 | 159 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 17.03 HSL | 20.036 | 159 | 159 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Ontwerpbegroting 2013 artikelonderdeel 17.04 ABvM | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties voorjaarsnota 2013 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 17.04 ABvM | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties Miljoenennota 2014 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 17.04 ABvM | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Ontwerpbegroting 2013 artikelonderdeel 17.06 PMR | 49.458 | 17.407 | 5.139 | 3.953 | 3.019 | 2.573 | 1.936 | 1.846 | 11.518 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties voorjaarsnota 2013 | – 21.666 | 352 | 12.103 | 12.079 | 12.060 | 51 | 39 | 37 | 386 | 61 | 78 | 68 | 100 | 99 | 102 | 2 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 17.06 PMR | 27.792 | 17.759 | 17.242 | 16.032 | 15.079 | 2.624 | 1.975 | 1.883 | 11.904 | 61 | 78 | 68 | 100 | 99 | 102 | 2 | |||
Indexering 2013 | Intens./extens. | 2.117 | 1.006 | 336 | 320 | 72 | 47 | 41 | 31 | 31 | 233 | 2 | |||||||
Mutaties Miljoenennota 2014 | 1.006 | 336 | 320 | 72 | 47 | 41 | 31 | 31 | 233 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 17.06 PMR | 28.798 | 18.095 | 17.562 | 16.104 | 15.126 | 2.665 | 2.006 | 1.914 | 12.137 | 61 | 78 | 68 | 100 | 99 | 102 | 2 | |||
Totaal uitgaven stand ontwerpbegroting 2013 Mega VenV | 54.157 | 23.407 | 11.139 | 3.953 | 3.019 | 2.573 | 1.936 | 1.846 | 11.518 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Totaal uitgaven stand eerste suppletoire wet 2013 Mega VenV | 50.435 | 23.873 | 23.356 | 16.032 | 15.079 | 2.624 | 1.975 | 1.883 | 11.904 | 61 | 78 | 68 | 100 | 99 | 102 | 2 | |||
Totaal uitgaven stand Miljoenennota 2014 Mega VenV | 58.664 | 24.368 | 23.835 | 16.104 | 15.126 | 2.665 | 2.006 | 1.914 | 12.137 | 61 | 78 | 68 | 100 | 99 | 102 | 2 | |||
Ontwerpbegroting 2013 artikelonderdeel 17.09 Ontvangsten Mega VenV | 3.000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties voorjaarsnota 2013 | – 1.901 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 17.09 Ontvangsten Mega VenV | 1.099 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties Miljoenennota 2014 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 17.09 Ontvangsten Mega VenV | 1.099 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Artikel 17 Megaprojecten Verkeer en Vervoer
-
2. IenM dekt in de ontwerpbegroting over 2014 het budgettaire probleem dat is ontstaan door het niet uitkeren van de prijsbijstelling uit de resterende Investeringsruimte per investeringsdomein. Er resteert dan een kasritmeprobleem. IenM lost dit uiterlijk bij ontwerpbegroting 2017 op, maar zo mogelijk eerder bij een eerstvolgende herijking van het Investeringsprogramma. Dit impliceert dat ex ante het risico wordt geaccepteerd dat ex post een kasoverschrijding van het Infrastructuurfonds optreedt van maximaal het minbedrag in het betreffende jaar. IenM zal er desalniettemin op sturen om binnen de aangepaste kasranden te blijven.
-
5. Deze mutatie betreft onderstaande verschuivingen over de diverse aanlegartikelen van het Infrastructuurfonds:
-
– Op artikelonderdeel 17.01 Westerscheldetunnel wordt voor de jaren 2013/2014 nog circa € 0,3 mln aan claims voor nadeelcompensatie verwacht. Dit bedrag is sterk afhankelijk van de uitspraak van de Raad van State. Na 2014 worden geen claims meer verwacht. Het restant kan daarom worden overgeheveld naar de investeringsruimte op 12.07;
-
– Een overboeking vanuit artikel 13 (Afdekking risico's spoorprogramma's) naar artikel 17 voor de financiering van de pilot geluidsmaatregelen Lansingerland. Dit in lijn met de voortgangsinformatie die eerder aan de Tweede Kamer is gezonden (Voortgangsrapportage 31 HSL);
-
– Een budgetoverheveling vanuit artikel 12 (project A4 Burgerveen–Leiden) naar artikel 17 HSL voor het schadeschap A4-HSL.
-
Categorie | Totaal mutatie | 2013 | 2014 | 2015 | 2016 | 2017 | 2018 | 2019 | 2020 | 2021 | 2022 | 2023 | 2024 | 2025 | 2026 | 2027 | 2028 | Toelichting | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Ontwerpbegroting 2013 artikelonderdeel 18.01 Saldo afgesl.rekg. | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties voorjaarsnota 2013 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 18.01 Saldo afgesl.rekg. | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties Miljoenennota 2014 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 18.01 Saldo afgesl.rekg. | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Ontwerpbegroting 2013 artikelonderdeel 18.02 Beter Benutten | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties voorjaarsnota 2013 | 0 | 0 | 50.000 | 125.000 | 125.000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 18.02 Beter Benutten | 0 | 0 | 50.000 | 125.000 | 125.000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties Miljoenennota 2014 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 18.02 Beter Benutten | 0 | 0 | 50.000 | 125.000 | 125.000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Ontwerpbegroting 2013 artikelonderdeel 18.03 Intermod.verv. | 3.196 | 2.000 | 3.000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties voorjaarsnota 2013 | – 882 | 3.965 | 57 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 18.03 Intermod.verv. | 2.314 | 5.965 | 3.057 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties Miljoenennota 2014 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 18.03 Intermod.verv. | 2.314 | 5.965 | 3.057 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Ontwerpbegroting 2013 artikelonderdeel 18.04 Geb. aanpak | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties voorjaarsnota 2013 | 2.374 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 18.04 Geb. aanpak | 2.374 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Overboeking binnen Infrastructuurfonds | Intens./extens. | 495 | 495 | 5 | |||||||||||||||
Mutaties Miljoenennota 2014 | 495 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 18.04 Geb. aanpak | 2.869 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Ontwerpbegroting 2013 artikelonderdeel 18.05 Railinfrabeh. | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties voorjaarsnota 2013 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 18.05 Railinfrabeh. | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties Miljoenennota 2014 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 18.05 Railinfrabeh. | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Ontwerpbegroting 2013 artikelonderdeel 18.06 Ext.veiligheid | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties voorjaarsnota 2013 | 1.013 | 2.526 | 2.000 | 2.009 | 2.000 | 1.000 | 1.000 | 898 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 18.06 Ext.veiligheid | 1.013 | 2.526 | 2.000 | 2.009 | 2.000 | 1.000 | 1.000 | 898 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties Miljoenennota 2014 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 18.06 Ext.veiligheid | 1.013 | 2.526 | 2.000 | 2.009 | 2.000 | 1.000 | 1.000 | 898 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Ontwerpbegroting 2013 artikelonderdeel 18.07 Mob.onafh. Kennis/Exp. | 42 | 42 | 42 | 42 | 42 | 42 | 42 | 42 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties voorjaarsnota 2013 | 222 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 18.07 Mob.onafh. Kennis/Exp. | 264 | 42 | 42 | 42 | 42 | 42 | 42 | 42 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties Miljoenennota 2014 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 18.07 Mob.onafh. Kennis/Exp. | 264 | 42 | 42 | 42 | 42 | 42 | 42 | 42 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Ontwerpbegroting 2013 artikelonderdeel 18.08 Netwerkoverst.kosten | 270.376 | 252.459 | 244.487 | 237.001 | 238.024 | 237.355 | 232.502 | 232.380 | 232.766 | 232.766 | 232.766 | 233.794 | 233.794 | 233.794 | 233.794 | 233.794 | |||
Mutaties voorjaarsnota 2013 | 396 | – 719 | – 760 | – 19.104 | – 38.492 | – 53.625 | – 53.656 | – 53.658 | – 53.403 | – 52.747 | – 52.386 | – 52.051 | – 51.352 | – 51.371 | – 51.307 | – 53.498 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 18.08 Netwerkoverst.kosten | 270.772 | 251.740 | 243.727 | 217.897 | 199.532 | 183.730 | 178.846 | 178.722 | 179.363 | 180.019 | 180.380 | 181.743 | 182.442 | 182.423 | 182.487 | 180.296 | |||
Indexering 2013 | Intens./extens. | 13.081 | 947 | 815 | 782 | 797 | 804 | 803 | 804 | 803 | 805 | 805 | 805 | 822 | 822 | 822 | 822 | 823 | 2 |
Netwerkoverstijgende kosten | Intens./extens. | 105.607 | 9.482 | 8.796 | 7.345 | 16.065 | 14.415 | 6.011 | 8.701 | 8.707 | 8.763 | 8.661 | 8.661 | 4 | |||||
Overboeking HXII – IF artikel 18 | Intens./extens. | 7.659 | 1.374 | 629 | 629 | 629 | 629 | 629 | 314 | 314 | 314 | 314 | 314 | 314 | 314 | 314 | 314 | 314 | 10 |
Loonbijstelling 2013 | Intens./extens. | 3.316 | 232 | 219 | 213 | 204 | 204 | 204 | 204 | 204 | 204 | 204 | 204 | 204 | 204 | 204 | 204 | 204 | 14 |
Overboeking HXII – IF artikel 18 | Intens./extens. | – 535.500 | – 35.700 | – 35.700 | – 35.700 | – 35.700 | – 35.700 | – 35.700 | – 35.700 | – 35.700 | – 35.700 | – 35.700 | – 35.700 | – 35.700 | – 35.700 | – 35.700 | – 35.700 | 27 | |
Mutaties Miljoenennota 2014 | 12.035 | – 25.241 | – 26.731 | – 18.005 | – 19.648 | – 28.053 | – 25.677 | – 25.672 | – 25.614 | – 25.716 | – 25.716 | – 34.360 | – 34.360 | – 34.360 | – 34.360 | – 34.359 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 18.08 Netwerkoverst.kosten | 282.807 | 226.499 | 216.996 | 199.892 | 179.884 | 155.677 | 153.169 | 153.050 | 153.749 | 154.303 | 154.664 | 147.383 | 148.082 | 148.063 | 148.127 | 145.937 | |||
Ontwerpbegroting 2013 artikelonderdeel 18.11 Investeringsruimte | 0 | 0 | 0 | 0 | 15.418 | 33.376 | 150.161 | 173.203 | 144.987 | 579.234 | 842.725 | 1.087.730 | 1.598.826 | 1.585.044 | 1.631.799 | 1.893.035 | |||
Mutaties voorjaarsnota 2013 | 0 | 0 | 0 | 0 | – 11.693 | – 25.311 | – 113.878 | – 131.353 | – 133.994 | – 579.234 | – 842.725 | – 1.087.731 | – 1.598.827 | – 1.585.044 | – 1.631.799 | – 1.893.036 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 18.11 Investeringruimte | 0 | 0 | 0 | 0 | 3.725 | 8.065 | 36.283 | 41.850 | 10.993 | 0 | 0 | – 1 | – 1 | 0 | 0 | – 1 | |||
Overbioeking HXII – IF KRW | Intens./extens. | – 100.917 | – 3.725 | – 8.065 | – 36.283 | – 41.850 | – 10.994 | 13 | |||||||||||
Mutaties Miljoenennota 2014 | 0 | 0 | 0 | 0 | – 3.725 | – 8.065 | – 36.283 | – 41.850 | – 10.994 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 18.11 Invest.ruimte | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | – 1 | 0 | 0 | – 1 | – 1 | 0 | 0 | – 1 | |||
Ontwerpbegroting 2013 artikelonderdeel 18.12 Nader toe te wijzen B&O&V | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 494.593 | 494.593 | 494.593 | 494.593 | 494.593 | 494.593 | 494.593 | 494.593 | |||
Mutaties voorjaarsnota 2013 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 9.371 | 9.371 | 9.371 | 9.371 | 9.371 | 9.371 | 9.371 | 9.371 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 18.12 Nader toe te wijzen B&O&V | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 503.964 | 503.964 | 503.964 | 503.964 | 503.964 | 503.964 | 503.964 | 503.964 | |||
DBFM A1/A6 SAA | Intens./extens. | – 67.140 | – 12.990 | – 12.990 | – 6.860 | – 6.860 | – 6.860 | – 6.860 | – 6.860 | – 6.860 | 20 | ||||||||
Areaalgroei (artikel 12) | Intens./extens. | – 386.534 | – 58.245 | – 58.245 | – 58.245 | – 58.245 | – 58.245 | – 31.770 | – 31.770 | – 31.770 | 25 | ||||||||
Baltic Ace | Intens./extens. | – 77.000 | – 77.000 | 26 | |||||||||||||||
Mutaties Miljoenennota 2014 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | – 148.235 | – 71.235 | – 65.105 | – 65.105 | – 65.105 | – 38.630 | – 38.630 | – 38.630 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 18.12 Nader toe te wijzen B&O&V | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 355.729 | 432.729 | 438.859 | 438.859 | 438.859 | 465.334 | 465.334 | 465.334 | |||
Ontwerpbegroting 2013 artikelonderdeel 18.13 Tol gefinanc.uitgaven | 0 | 0 | 0 | 0 | 0 | 0 | 18.083 | 18.083 | 30.462 | 30.462 | 40.383 | 40.383 | 40.383 | 40.383 | 40.383 | 40.383 | |||
Mutaties voorjaarsnota 2013 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 18.13 Tol gefinanc.uitgaven | 0 | 0 | 0 | 0 | 0 | 0 | 18.083 | 18.083 | 30.462 | 30.462 | 40.383 | 40.383 | 40.383 | 40.383 | 40.383 | 40.383 | |||
Aanpassing tolreeksen naar prijspeil 2013 en verhoging NWO. | Desaldering | 69.862 | 649 | 649 | 1.093 | 1.093 | 11.063 | 11.063 | 11.063 | 11.063 | 11.063 | 11.063 | 28 | ||||||
Mutaties Miljoenennota 2014 | 0 | 0 | 0 | 0 | 0 | 0 | 649 | 649 | 1.093 | 1.093 | 11.063 | 11.063 | 11.063 | 11.063 | 11.063 | 11.063 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 18.13 Tol gefinanc.uitgaven | 0 | 0 | 0 | 0 | 0 | 0 | 18.732 | 18.732 | 31.555 | 31.555 | 51.446 | 51.446 | 51.446 | 51.446 | 51.446 | 51.446 | |||
Totaal uitgaven stand ontwerpbegroting 2013 Overige uitg.en ontv. | 273.614 | 254.501 | 247.529 | 237.043 | 253.484 | 270.773 | 400.788 | 423.708 | 902.808 | 1.337.055 | 1.610.467 | 1.856.500 | 2.367.596 | 2.353.814 | 2.400.569 | 2.661.805 | |||
Totaal uitgaven stand eerste suppletoire wet 2013 Overige uitg.en ontv. | 276.738 | 260.273 | 298.826 | 344.948 | 330.299 | 192.837 | 234.254 | 239.595 | 724.782 | 714.445 | 724.727 | 726.089 | 726.788 | 726.770 | 726.834 | 724.642 | |||
Totaal uitgaven stand Miljoenennota 2014 Overige uitg.en ontv. | 289.268 | 235.032 | 272.095 | 326.943 | 306.926 | 156.719 | 172.943 | 172.722 | 541.032 | 618.587 | 644.969 | 637.687 | 638.386 | 664.843 | 664.907 | 662.716 | |||
Ontwerpbegroting 2013 artikelonderdeel 18.09 Ontvangsten | 0 | 0 | 0 | 0 | 0 | 0 | 18.083 | 18.083 | 30.462 | 30.462 | 40.383 | 40.383 | 40.383 | 40.383 | 40.383 | 40.383 | |||
Mutaties voorjaarsnota 2013 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 18.09 Ontvangsten Overige uitg.en ontv. | 0 | 0 | 0 | 0 | 0 | 0 | 18.083 | 18.083 | 30.462 | 30.462 | 40.383 | 40.383 | 40.383 | 40.383 | 40.383 | 40.383 | |||
Aanpassing tolreeksen naar prijspeil 2013 en verhoging NWO. | Desaldering | 69.862 | 649 | 649 | 1.093 | 1.093 | 11.063 | 11.063 | 11.063 | 11.063 | 11.063 | 11.063 | 28 | ||||||
Mutaties Miljoenennota 2014 | 0 | 0 | 0 | 0 | 0 | 0 | 649 | 649 | 1.093 | 1.093 | 11.063 | 11.063 | 11.063 | 11.063 | 11.063 | 11.063 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 18.09 Ontvangsten Overige uitg.en ontv. | 0 | 0 | 0 | 0 | 0 | 0 | 18.732 | 18.732 | 31.555 | 31.555 | 51.446 | 51.446 | 51.446 | 51.446 | 51.446 | 51.446 | |||
Ontwerpbegroting 2013 artikelonderdeel 18.10 Voordelig saldo | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties voorjaarsnota 2013 | 147.317 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 18.10 Voordelig saldo | 147.317 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Mutaties Miljoenennota 2014 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 18.10 Voordelig saldo | 147.317 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||
Totaal ontvangsten stand ontwerpbegroting 2013 Overige uitg.en ontv. | 0 | 0 | 0 | 0 | 0 | 0 | 18.083 | 18.083 | 30.462 | 30.462 | 40.383 | 40.383 | 40.383 | 40.383 | 40.383 | 40.383 | |||
Totaal ontvangsten stand eerste suppletoire wet 2013 Overige uitg.en ontv. | 147.317 | 0 | 0 | 0 | 0 | 0 | 18.083 | 18.083 | 30.462 | 30.462 | 40.383 | 40.383 | 40.383 | 40.383 | 40.383 | 40.383 | |||
Totaal ontvangsten stand Miljoenennota 2014 Overige uitg.en ontv. | 147.317 | 0 | 0 | 0 | 0 | 0 | 18.732 | 18.732 | 31.555 | 31.555 | 51.446 | 51.446 | 51.446 | 51.446 | 51.446 | 51.446 |
Artikel 18 Overige uitgaven en ontvangsten
-
2. IenM dekt in de ontwerpbegroting over 2014 het budgettaire probleem dat is ontstaan door het niet uitkeren van de prijsbijstelling uit de resterende Investeringsruimte per investeringsdomein. Er resteert dan een kasritmeprobleem. IenM lost dit uiterlijk bij ontwerpbegroting 2017 op, maar zo mogelijk eerder bij een eerstvolgende herijking van het Investeringsprogramma. Dit impliceert dat ex ante het risico wordt geaccepteerd dat ex post een kasoverschrijding van het Infrastructuurfonds optreedt van maximaal het minbedrag in het betreffende jaar. IenM zal er desalniettemin op sturen om binnen de aangepaste kasranden te blijven.
-
4. In 2009 is heeft het ministerie van Financiën toestemming verleend om een deel van de vordering van RWS op IenM in een periode van 15 jaar af te betalen. Hiervoor is een 15-jarige kasreeks in de begroting opgenomen. Deze reeks is technisch opgenomen in artikel 12.02 (Beheer en Onderhoud). Deze bijdrage is echter niet voor Beheer en Onderhoud bedoeld. Voorgesteld wordt om de afbetalingsreeks op te nemen in artikel 18.08.02 (Overige netwerkoverstijgende kosten).
-
5. Deze mutatie houdt verband met een afrekening Hollandse Brug OV SAAL-RRAAM: Met betrekking tot de Hollandse brug variant in relatie tot OV SAAL MT is afgesproken dat van het geraamde budget ad circa € 1,8 mln OV SAAL 2/3 voor haar rekening neemt (Infrastructuurfonds begrotingsartikel 13) en RRAAM 1/3 (Infrastructuurfonds begrotingsartikel 18). De totale realisatie bedraagt uiteindelijk € 1,7 mln. Volgens de verdeelsleutel vindt een budgettaire compensatie plaats van afgerond € 495.000 vanuit OV SAAL naar RRAAM.
-
10. Tussen de begroting van HXII en dit artikel worden de volgende overboekingen aangebracht:
-
– De overdracht van 3,9 fte’s van de Hoofddirectie Bestuurlijke en Juridische Zaken (HBJZ) naar RWS (€ 0,3 mln);
-
– Een vergoeding aan RWS voor de 1 procent regeling voor mensen met afstand tot arbeidsmarkt (€ 0,3 mln);
-
– Een overboeking van 0,5 fte naar RWS/PPS/DBFM (€ 0,1 mln);
-
– Een overboeking van € 0,1 mln voor depotruimte Nationaal Archief;
-
– Opdrachtverstrekking aan Deltares voor verschillende Rijkscoördinatieregelingprojecten (RCR) (€ 0,1 mln);
-
– De overdracht van het personeel belast met de ARBO-taken van SSO/HRM naar RWS (€ 0,5 mln structureel);
-
– Overboeking van ministerie van EZ voor aanvullende opdracht aan SPA Deltares wegens verschillende RCR projecten (€ 0,3 mln);
-
– Een overboeking van DCO naar RWS voor de campagne van A naar Beter (€ 0,1 mln);
-
– Een bijdrage van RWS van in totaal bijna 0,3 mln per jaar (uit de artikelen 12, 15 en 18) aan de opdracht PDOK aan het Kadaster en Geonovum voor de jaren 2013–2016.
-
-
13. De resterende programmaruimte op dit artikel (€ 100 mln) wordt overgeboekt naar de begroting van HXII en betrokken bij het oplossen van de KRW-problemen (Kaderrichtlijn Water). Een daarvoor benodigde kasschuif wordt aangebracht via het Deltafonds.
-
14. Dit is de toevoeging aan het Infrastructuurfonds van het uitgekeerde deel van de loonbijstelling 2013. Het betreft de hogere uitgaven voor de werkgever aan ouderdoms- en nabestaandenpensioen en een stijging van de bijdrage in het kader van de Zorgverzekeringswet.
-
20. Bij het DBFM-contract voor het project A1/A6 Schiphol Amsterdam Almere heeft de «financial close» plaatsgevonden, dit is budgettair verwerkt.
-
25. Dit betreft het treffen van een reservering voor consequenties areaalgroei op beheer en onderhoud wegen onder planuitwerking vanuit de Investeringsruimte wegen en vanuit de bestaande reservering op artikel 18.12. Voor een nadere toelichting wordt verwezen naar «Bijlage 5 Beheer en Onderhoud».
-
26. Op 5 december 2012 is de Baltic Ace na een aanvaring met de Corvus J gezonken in de vaarroute naar Rotterdam, 65 km ten westen van Goeree. Het scheepswrak bedreigt het mariene milieu en een vlot en veilig scheepvaartverkeer. Op dit gedeelte van de Noordzee is dit een verantwoordelijkheid van IenM/RWS. Dekking van de bergingskosten komt uit Vervanging en Renovaties in 2021.
-
27. De inkomsten die in de begroting stonden voor Het Rijksvastgoed- en ontwikkelingsbedrijf (RVOB) worden overgebracht naar IenM. Het gaat hierbij om inkomsten uit areaal waarop RWS het materieel respectievelijk feitelijk beheer uitvoert. Extra opbrengsten die IenM (RWS) realiseert bovenop dit bedrag kunnen door IenM (RWS) ingezet worden. De middelenoverboeking van RVOB naar IenM (RWS) betreft in totaal € 35,7 mln per jaar. Deze overboeking wordt zichtbaar bij de opbrengst derden in de staat van baten en lasten en is als volgt opgebouwd: € 19,5 mln structurele ontvangsten uit de pacht van «benzinestations, € 11,5 mln structurele ontvangsten uit de ingebruikgeving van RWS areaal (huur, pacht) en € 4,7 mln structurele ontvangsten uit incidentele verkoop van RWS areaal. De bijdrage van de begroting van Hoofdstuk XII aan het Infrastructuurfonds alsmede de Overige netwerkoverstijgende kosten op het Infrastructuurfonds (artikel 18.08 «Apparaatskosten Rijkswaterstaat») worden overeenkomstig verlaagd met € 35,7 mln.
-
28. De tolreeksen zijn geïndexeerd naar prijspeil 2013. Daarnaast is de tolopgave van de NWO verhoogd naar € 300 mln. De gehanteerde IBOI cijfers zijn 1,895% voor 2012 en 1,659% voor 2013.
Categorie | Totaal mutatie | 2013 | 2014 | 2015 | 2016 | 2017 | 2018 | 2019 | 2020 | 2021 | 2022 | 2023 | 2024 | 2025 | 2026 | 2027 | 2028 | Toelichting | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Ontwerpbegroting 2013 artikelonderdeel 19.09 | 5.879.349 | 6.608.356 | 5.640.937 | 5.877.752 | 6.039.905 | 5.806.026 | 6.037.906 | 6.105.183 | 5.467.346 | 5.715.923 | 5.716.664 | 5.617.274 | 5.599.948 | 5.602.233 | 5.602.201 | 5.596.070 | |||
Mutaties voorjaarsnota 2013 | – 67.129 | – 86.717 | – 105.200 | – 110.432 | – 142.130 | – 164.083 | – 164.083 | – 164.083 | – 164.083 | – 164.083 | – 164.083 | – 164.083 | – 164.083 | – 164.083 | – 164.083 | – 164.083 | |||
Stand eerste suppletoire wet 2013 artikelonderdeel 19.09 | 5.812.220 | 6.521.639 | 5.535.737 | 5.767.320 | 5.897.775 | 5.641.943 | 5.873.823 | 5.941.100 | 5.303.263 | 5.551.840 | 5.552.581 | 5.453.191 | 5.435.865 | 5.438.150 | 5.438.118 | 5.431.987 | |||
Indexering 2013 | Intens./extens. | 2.616 | 189 | 163 | 156 | 159 | 161 | 161 | 322 | 0 | 322 | 0 | 161 | 165 | 165 | 164 | 328 | 2 | |
Overboeking HXII – IF artikel 12 | Intens./extens. | – 13.325 | – 3.470 | – 174 | – 374 | – 3.443 | – 5.512 | – 32 | – 32 | – 32 | – 32 | – 32 | – 32 | – 32 | – 32 | – 32 | – 32 | – 32 | 6 |
Overboeking HXII – IF artikel 13 | Intens./extens. | – 11.400 | – 2.500 | – 2.900 | – 6.000 | 9 | |||||||||||||
Overboeking HXII – IF artikel 18 | Intens./extens. | 10.659 | 1.374 | 829 | 829 | 829 | 829 | 829 | 514 | 514 | 514 | 514 | 514 | 514 | 514 | 514 | 514 | 514 | 10 |
Overboeking HXII – IF artikel 14 | Intens./extens. | – 7.262 | – 2.500 | – 4.762 | 11 | ||||||||||||||
Overbioeking HXII – IF KRW | Intens./extens. | – 100.917 | – 3.725 | – 8.065 | – 36.283 | – 41.850 | – 10.994 | 13 | |||||||||||
Loonbijstelling 2013 | Intens./extens. | 24.142 | 1.804 | 1.591 | 1.555 | 1.387 | 1.514 | 1.481 | 1.481 | 1.481 | 1.481 | 1.481 | 1.481 | 1.481 | 1.481 | 1.481 | 1.481 | 1.481 | 14 |
Overboeking HXII – IF artikel 15 | Intens./extens. | 457 | – 1.762 | 2.298 | – 37 | – 42 | 15 | ||||||||||||
DBFM N33 Assen–Zuidbroek | Intens./extens. | 8.161 | – 60.156 | – 75.946 | 10.275 | 10.275 | 10.275 | 10.275 | 10.275 | 10.292 | 10.292 | 10.292 | 10.292 | 10.292 | 10.357 | 10.357 | 10.357 | 10.357 | 18 |
DBFM A1/A6 SAA | Intens./extens. | – 88.303 | – 12.787 | – 45.746 | – 170.058 | – 436.003 | 127.051 | 46.847 | 40.717 | 40.717 | 39.987 | 39.987 | 40.174 | 40.174 | 40.174 | 40.174 | 40.174 | 40.115 | 20 |
Overboeking HXII – IF artikel 18 | Intens./extens. | – 535.500 | – 35.700 | – 35.700 | – 35.700 | – 35.700 | – 35.700 | – 35.700 | – 35.700 | – 35.700 | – 35.700 | – 35.700 | – 35.700 | – 35.700 | – 35.700 | – 35.700 | – 35.700 | 27 | |
Mutaties Miljoenennota 2014 | – 77.308 | – 158.085 | – 199.354 | – 467.300 | 94.893 | 15.796 | – 18.706 | – 24.578 | 5.870 | 16.542 | 16.890 | 16.894 | 16.959 | 16.958 | 17.122 | 16.735 | |||
Stand ontwerpbegroting 2014 artikelonderdeel 19.09 | 5.734.912 | 6.363.554 | 5.336.383 | 5.300.020 | 5.992.668 | 5.657.739 | 5.855.117 | 5.916.522 | 5.309.133 | 5.568.382 | 5.569.471 | 5.470.085 | 5.452.824 | 5.455.108 | 5.455.240 | 5.448.722 | |||
Totaal uitgaven stand ontwerpbegroting 2013 HWN | 5.879.349 | 6.608.356 | 5.640.937 | 5.877.752 | 6.039.905 | 5.806.026 | 6.037.906 | 6.105.183 | 5.467.346 | 5.715.923 | 5.716.664 | 5.617.274 | 5.599.948 | 5.602.233 | 5.602.201 | 5.596.070 | |||
Totaal ontvangsten stand eerste suppletoire wet 2013 | 5.812.220 | 6.521.639 | 5.535.737 | 5.767.320 | 5.897.775 | 5.641.943 | 5.873.823 | 5.941.100 | 5.303.263 | 5.551.840 | 5.552.581 | 5.453.191 | 5.435.865 | 5.438.150 | 5.438.118 | 5.431.987 | |||
Totaal ontvangsten stand Miljoenennota 2014 | 5.734.912 | 6.363.554 | 5.336.383 | 5.300.020 | 5.992.668 | 5.657.739 | 5.855.117 | 5.916.522 | 5.309.133 | 5.568.382 | 5.569.471 | 5.470.085 | 5.452.824 | 5.455.108 | 5.455.240 | 5.448.722 |
Artikel 19 Bijdragen andere begrotingen Rijk
-
2. IenM dekt in de ontwerpbegroting over 2014 het budgettaire probleem dat is ontstaan door het niet uitkeren van de prijsbijstelling uit de resterende Investeringsruimte per investeringsdomein. Er resteert dan een kasritmeprobleem. IenM lost dit uiterlijk bij ontwerpbegroting 2017 op, maar zo mogelijk eerder bij een eerstvolgende herijking van het Investeringsprogramma. Dit impliceert dat ex ante het risico wordt geaccepteerd dat ex post een kasoverschrijding van het Infrastructuurfonds optreedt van maximaal het minbedrag in het betreffende jaar. IenM zal er desalniettemin op sturen om binnen de aangepaste kasranden te blijven.
-
6. Tussen de begroting van HXII en artikel 12 worden de volgende overboekingen aangebracht:
-
– Subsidieregeling Euro-VI (schone motoren vrachtwagens en bussen): voor 2013 wordt een bedrag van € 5 mln overgeheveld. De uitvoering van deze regeling wordt verantwoord op artikel 20 in de begroting van HXII;
-
– Beter Benutten: vanuit artikel 12 Beter benutten vindt een overboeking plaats naar de Begroting van HXII voor programmakosten en externe inhuur door het verlengen van de projectduur (in totaal € 1,2 mln). Tevens worden vanuit de Begroting van hoofdstuk XII de in 2012 onbesteed gebleven gelden voor Beter Benutten (circa € 0,8 mln) teruggeboekt naar artikel 12 in het fonds voor het in standhouden van het projecttotaal van Beter Benutten.
-
– Bijdrage van RWS (uit de artikelen 12, 15 en 18) aan de opdracht PDOK aan het Kadaster en Geonovum voor de jaren 2013–2016 (bijna € 0,3 mln per jaar);
-
– Een overboeking naar het ministerie van BZK voor de elektronische publicatie van verkeersbesluiten (€ 0,1 mln) en een overboeking vanuit de Begroting van HXII (€ 0,9 mln) in dit kader.
-
-
9. Uit artikel 13 worden de volgende overboekingen naar de Begroting van hoofdstuk XII aangebracht voor:
-
– Gelden voor het onderzoek Roadmap ERTMS (€ 2,5 mln);
-
– De BDU voor de verlenging Spoorlijn van Roodeschool naar Eemshaven (€ 2,9 mln).
-
-
10. Tussen de begroting van HXII en artikel 18 worden de volgende overboekingen aangebracht:
-
– De overdracht van 3,9 fte’s van de Hoofddirectie Bestuurlijke en Juridische Zaken (HBJZ) naar RWS (€ 0,3 mln);
-
– Een vergoeding aan RWS voor de 1 procent regeling voor mensen met afstand tot arbeidsmarkt (€ 0,3 mln);
-
– Een overboeking van 0,5 fte naar RWS/PPS/DBFM (€ 0,1 mln);
-
– Een overboeking van € 0,1 mln voor depotruimte Nationaal Archief en
-
– Opdrachtverstrekking aan Deltares voor verschillende Rijkscoördinatieregelingprojecten (RCR) (€ 0,1 mln)
-
– De overdracht van het personeel belast met de ARBO-taken van SSO/HRM naar RWS (€ 0,5 mln structureel);
-
– Overboeking van het ministerie van EZ voor een aanvullende opdracht aan SPA Deltares wegens verschillende RCR projecten (€ 0,3 mln);
-
– Een overboeking van DCO naar RWS voor de campagne van A naar Beter (€ 0,1 mln);
-
– Een bijdrage van RWS (uit de artikelen 12, 15 en 18) aan de opdracht PDOK aan het Kadaster en Geonovum voor de jaren 2013–2016 (bijna € 0,3 mln per jaar).
-
-
11. De BDU voor het jaar 2013 is in december 2012 vastgesteld. Daarin is overeenkomstig de gebruikelijke werkwijze een forfaitaire index opgenomen. Vanuit artikel 14 Regionaal/lokale infrastructuur wordt dekking geboden voor het niet uitkeren van de prijsindex en overgeboekt naar de begroting van HXII.
-
13. De resterende programmaruimte op dit artikel (€ 100 mln) wordt overgeboekt naar de begroting van HXII en betrokken bij het oplossen van de KRW-problemen (Kaderrichtlijn Water). Een daarvoor benodigde kasschuif wordt aangebracht via het Deltafonds.
-
14. Dit is de toevoeging aan het Infrastructuurfonds van het uitgekeerde deel van de loonbijstelling 2013. Het betreft de hogere uitgaven voor de werkgever aan ouderdoms- en nabestaandenpensioen en een stijging van de bijdrage in het kader van de Zorgverzekeringswet.
-
15. Via de decentralisatie-uitkering Binnenhavens ontvangt de gemeente Waalwijk € 4,6 mln. Deze gemeente kan de eventueel betaalde BTW terugvorderen via het BTW-compensatiefonds. De genoemde gemeente heeft een plan ingediend waarmee het landelijke netwerk van overslagvoorzieningen voor containervervoer over water wordt versterkt. De aanvraag voldoet hiermee aan de gestelde randvoorwaardelijke criteria. Uit artikel 15 wordt via de Begroting van hoofdstuk XII daarom in totaal € 5 mln overgeboekt naar het Gemeente- en BTW Compensatiefonds.
Voorts wordt een bijdrage van RWS (uit de artikelen 12, 15 en 18) aan de opdracht PDOK aan het Kadaster en Geonovum voor de jaren 2013–2016 (bijna € 0,3 mln per jaar) alsmede een bijdrage voor Caribisch Nederland/BES voor investeringen in een Maritieme incidentenorganisatie (totaal € 6 mln) naar de begroting van HXII overgeboekt.
-
18. Bij het DBFM-contract (Design, Build, Finance & Maintain) voor het project N33 Assen-Zuidbroek heeft de «financial close» plaatsgevonden. Op verzoek van het Ministerie van Financiën wordt hier een proef uitgevoerd waarbij inflatiegerelateerde vergoedingen wordt uitbetaald. Een consequentie van deze proef is dat de mijlpaalvergoeding binnen het contract gemaximaliseerd is op 5 procent van de investeringssom.
-
20. Bij het DBFM-contract voor het project A1/A6 Schiphol Amsterdam Almere heeft de «financial close» plaatsgevonden, dit is budgettair verwerkt.
-
27. De inkomsten die in de begroting stonden voor Het Rijksvastgoed- en ontwikkelingsbedrijf (RVOB) worden overgebracht naar IenM. Het gaat hierbij om inkomsten uit areaal waarop RWS het materieel respectievelijk feitelijk beheer uitvoert. Extra opbrengsten die IenM (RWS) realiseert bovenop dit bedrag kunnen door IenM (RWS) ingezet worden. De middelenoverboeking van RVOB naar IenM (RWS) betreft in totaal € 35,7 mln per jaar. Deze overboeking wordt zichtbaar bij de opbrengst derden in de staat van baten en lasten en is als volgt opgebouwd: € 19,5 mln structurele ontvangsten uit de pacht van «benzinestations, € 11,5 mln structurele ontvangsten uit de ingebruikgeving van RWS areaal (huur, pacht) en € 4,7 mln structurele ontvangsten uit incidentele verkoop van RWS areaal. De bijdrage van de begroting van Hoofdstuk XII aan het Infrastructuurfonds alsmede de Overige netwerkoverstijgende kosten op het Infrastructuurfonds (artikel 18.08 «Apparaatskosten Rijkswaterstaat») worden overeenkomstig verlaagd met € 35,7 mln.